Ventilated Only Space Simulation

NC-2009 EAc1:Optimize Energy Performance
posted by  TOMAS URIBE  on 

Hello Marcus! In the HVAC design of a project, there is a space where supply ventilation is included in order to accomplish the minimum amount of air required by ASHRAE 62.1-2007 standard.

5
Senior Sustainability Manager
ISG plc
LEEDuser Basic Member
0 thumbs up
Fri Oct 2, 2015, 8:16 pm

Rounding of Percent Energy Cost Savings for EAc1 Points

NC-2009 EAc1:Optimize Energy Performance
posted by  Joseph Chappell  on 

Hi all, We recently received a final design review where our percent energy cost savings have been corrected by the reviewer to show 31.95%.

11
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Sep 14, 2015, 2:04 pm

Process Energy Savings - Exceptional Calculation - Dry Coolers

NC-2009 EAc1:Optimize Energy Performance
posted by  MYRON JORDAN  on 

My inquiry is based upon reducing the energy consumption of a chilled water system which is being used in a manufacturing facility.

3
Thu Sep 3, 2015, 6:30 pm

free waste heat from outside of LEED project for heating

NC-2009 EAc1:Optimize Energy Performance
posted by  Mónika Egyed  on 

Our project is a small office building in Europe, on site of a great industrial plant with the same owner. The office building aims to achieve LEED Gold certification, while the plant does not.

4
Chief Engineer
Lile Engineering, LLC
LEEDuser Basic Member
59 thumbs up
Tue Sep 1, 2015, 5:27 pm

Renovation project Envelope question

NC-2009 EAc1:Optimize Energy Performance
posted by  Saju Varghese  on 

I'm not really sure how the envelope should be input in baseline vs. proposed.

3
SUSTAINABILITY COORDINATOR
JALRW Eng. Group Inc.
LEEDuser Basic Member
24 thumbs up
Thu Aug 20, 2015, 5:59 pm

2 energy point requirement

NC-2009 EAc1:Optimize Energy Performance
posted by  Mike Stopka  on 

I just wanted to verify that "Two (2) points mandatory for all LEED for New Construction projects registered after June 26, 2007" rule is no longer in effect. Referring to this: http://www.usgbc.o

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Aug 18, 2015, 2:08 pm

Questions about High-rise residential LEED Energy Modeling

NC-2009 EAc1:Optimize Energy Performance
posted by  Tommy Xing  on 

Hi, I’m working on a High-rise residential LEED energy modeling project now. I have a question regarding the lighting.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 9, 2015, 5:44 pm

LEED documentation with IES-VE

NC-2009 EAc1:Optimize Energy Performance
posted by  Mark Benson  on 

For EAp2/EAc1, what specific documentation does GBCI expect to see from a model built in IES VE?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Jun 3, 2015, 7:26 pm

Are exceptions mandatory or optional?

NC-2009 EAc1:Optimize Energy Performance
posted by  John Krutko  on 

Under ASHRAE 90.1 - G3.1.1 do I HAVE to use exception C for any zones having special pressurization relationships, cross contamination requirements, or code-required minimum circulation rates?

3
Default Avatar
Sr Project Manager
Osborn Engineering
LEEDuser Basic Member
1 thumbs up
Wed Apr 29, 2015, 1:23 pm

Yet another exhaust question

NC-2009 EAc1:Optimize Energy Performance
posted by  Lawrence Lile  on 

We've got an 11,000 square foot maintenance garage for trucks, modeling it under LEED and ASHRAE 90.1-2007.

7
Chief Engineer
Lile Engineering, LLC
LEEDuser Basic Member
59 thumbs up
Mon Apr 20, 2015, 3:42 pm