District / Campus Energy - Modeling Option 2 (Full accounting)
NC-2009 EAp2:Minimum energy performanceposted by Maya Karkour on
Dear All, I am intending to model a building on campus which is connected to a campus energy system providing chilled water and hot water.
Baseline Fan Adjustment
NC-2009 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Greetings, There is an issue I'd like to ask some advice about it. It is for Baseline fan adjustment.
Diversity factor of Server machine
NC-2009 EAp2:Minimum energy performanceposted by Sivarajah Ragulakeethan on
Hi, We are working on a LEED New Construction for Data Center project. I would like to confirm on my understanding. How much can we use as diversity factor for server machine?
ASHRAE Advanced Energy Design Guide - Mixed office/warehouse bld
NC-2009 EAp2:Minimum energy performanceposted by Michael Smithing on
We're looking at a building that will have approximately 10,000 sqft. of office space and 10,000 sqft. of warehouse space.
90.1-2007 Table G3.1.1A for Additions and Alterations
NC-2009 EAp2:Minimum energy performanceposted by Evelyn Dicks, EI, CxA on
Do the requirements of Table G3.1.1A Baseline HVAC System Types apply to the whole building or just to the project area for additions and alterations?
Appendix G-Baseline HVAC System
NC-2009 EAp2:Minimum energy performanceposted by Kristin Heinz on
Our project is a bed-and-breakfast with guest rooms that are conditioned using PTHP units. A VRF system conditions the common areas with a DOAS that uses a chiller and hot water boiler.
Baseline HVAC Selection
NC-2009 EAp2:Minimum energy performanceposted by April Rice on
We have a 5 story non-residential building (located on a campus), with a mechanical penthouse (with roof) above.
Baseline System 9 fan details
NC-2009 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Greetings, We have zones in our project which are addressed to system 9 (heating only).
Exceptional Calculation for Elevator
NC-2009 EAp2:Minimum energy performanceposted by Thomas Hellmann on
My read on ASHRAE-90.1 and numerous forums, is that USGBC may allow for an exceptional calculation to be performed for elevator energy savings, provided that; 1) Schedule of operation remains the s
Suspended Ceiling
NC-2009 EAp2:Minimum energy performanceposted by Omar Elrawy on
Dear all, I have a suspended ceiling with a 60 cm air gap between the panels and the reinforced concrete slab where all the electro-mechanical lies, but it doesn't act as plenum zone si