NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Nelina Loiselle on
To satisfy the LEED requirements, does every room in a hotel have to be commissioned?
OPR Never Produced
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Ed Clark on
I was added to the project after construction due to staffing changes. An OPR was never produced. The design meets and exceeds the owner's goals and commissioning has been completed.
Required Number of Construction Inspections?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Benjamin Tressler on
Does LEED specify a required number of commissioning inspections during construction? We are trying to develop a scope based on the minimum requirements of LEED.
Contract between the Owner and the CxA
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Mohamed M. Abd Elhameed on
For pursuing EAc3, the contract between the owner and the CxA ensuring CxA involvement in post-construction shall be uploaded through LEED Online credit form.
Design Engineer for EAp1 and CxA for EAc3
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Amy Harmon on
I've got a new building that is less than 50,000 SF.
CxA in projects over 50000
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Felipe Martinez on
Can the CxA in a project over 50000 ft^2 be someone from the MEPFP design team? Thank you in advance.
MANDATORY REQUIREMENTS AHSRAE 90.1
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Jorge Torres-Coto on
Does anyone know if isolation valves on a multiple chiller plant are required by ASHRAE, or they simply best practice? I have looked into this in ASHRAE documents, but have not found anything yet.
Language of Documents
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Catalina A on
Does anyone know how the documents and technical specifications of the different projects (HVAC, Electricity, Lighting, hot water, etc.) have to be presented to the GBCI in terms of language?