Sample LEED 2009 Basis of Design Document
NC-2009 EAp1:Fundamental commissioning of building energy systemsposted by Robert Shields on
I have a sample Basis of Design document that applies to LEED 2.2. Not sure if there are any differences in the requirements for the document required in LEED 2009.
Motorized Gravity Dampers ASHRAE 90.1 Mandatory Requirement
NC-2009 EAp1:Fundamental commissioning of building energy systemsposted by Jorge Torres-Coto on
Per the Mandatory Requirement of ASHRAE 90.1-2007 section 6.4.3.4.2 a gravity vent is required to be equipped with dampers that shut automatically. Though the 90.1 does not have an exception if th
Sample Commisioned Projects Criteria
NC-2009 EAp1:Fundamental commissioning of building energy systemsposted by Jalal Avades on
What are the requirements/criteria to meet the 'Representative Projects'?
Functional Performance Testing
NC-2009 EAp1:Fundamental commissioning of building energy systemsposted by Giulia Faccio on
Our project, registered under LEED 2009 Italia NC, consists in a building whose occupancy will take place in October 2014.
Duct Insulation to meet ASHRAE 90.1
NC-2009 EAp1:Fundamental commissioning of building energy systemsposted by Ralph Bicknese on
We have a condition at where the contractor has asked to use blue duct for underground locations in lieu of Armaflex insulation and concrete encasement.
Systems Manual
NC-2009 EAp1:Fundamental commissioning of building energy systemsposted by Michael Lofroos on
Although it is the requirement of the Commissioning Agent to develop the Systems Manual, Operation & Maintenance Systems manuals, can he/she delegate that responsibility to the General Contract
Commissioning required for a CHP?
NC-2009 EAp1:Fundamental commissioning of building energy systemsposted by André Harms on
One of our factory projects is planning on installing a CHP (combined heat and power) plant, with natural gas as the fuel source. Does this system require commissioning?
Chiller
NC-2009 EAp1:Fundamental commissioning of building energy systemsposted by Saju Varghese on
Should the chiller be considered part of the commisioning and M&V metering even if it's serving other tenants as well?