NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Nelina Loiselle  on 

To satisfy the LEED requirements, does every room in a hotel have to be commissioned?

0

OPR Never Produced

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Ed Clark  on 

I was added to the project after construction due to staffing changes. An OPR was never produced. The design meets and exceeds the owner's goals and commissioning has been completed.

1
Wed Jan 23, 2013, 4:56 pm
1
Fri Oct 8, 2010, 3:02 pm

Required Number of Construction Inspections?

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Benjamin Tressler  on 

Does LEED specify a required number of commissioning inspections during construction? We are trying to develop a scope based on the minimum requirements of LEED.

1
Tue Sep 27, 2011, 1:52 am

Contract between the Owner and the CxA

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Mohamed M. Abd Elhameed  on 

For pursuing EAc3, the contract between the owner and the CxA ensuring CxA involvement in post-construction shall be uploaded through LEED Online credit form.

1
Sun Apr 13, 2014, 2:53 pm
1
Fri Jul 22, 2016, 5:23 pm

CxA in projects over 50000

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Felipe Martinez  on 

Can the CxA in a project over 50000 ft^2 be someone from the MEPFP design team? Thank you in advance.

1
Fri Jul 11, 2014, 4:26 pm

MANDATORY REQUIREMENTS AHSRAE 90.1

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Jorge Torres-Coto  on 

Does anyone know if isolation valves on a multiple chiller plant are required by ASHRAE, or they simply best practice? I have looked into this in ASHRAE documents, but have not found anything yet.

1
Thu Jan 26, 2017, 8:44 pm
1
Wed Nov 24, 2010, 7:01 pm

Language of Documents

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Catalina A  on 

Does anyone know how the documents and technical specifications of the different projects (HVAC, Electricity, Lighting, hot water, etc.) have to be presented to the GBCI in terms of language?

1
Tue Jun 28, 2011, 5:01 pm