For the EAp1 form, I'm confused as to whether I am supposed to fill out this form for the design preliminary review, because this is a Construction credit? Can someone please clarify? Same applies to other "Construction" review credits. What is the typical method for this?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Michelle Rosenberger
PartnerArchEcology
522 thumbs up
August 14, 2013 - 5:11 pm
Hi Nicole,
If you are doing a split submittal, than no you don't. You only fill out the Design credits for the Design submittal. You will do a secondary Construction review for all of the Construction credits and whatever was deferred from Design.