Equipments to be Commissioned for Fundamental Commissioning

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Daisuke Miura  on 

Hi, I have a question regarding the scope of equipments to be commissioned for Fundamental Commissioning. 

1
Thu Oct 24, 2024, 10:28 am

Performing Commissioning Activities 3 years after occupancy

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Gaston Viau  on 

Hi!

Our NC-2009 project it's a 16,000sqf office building located in California.

5
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Tue Feb 20, 2024, 8:01 pm

Change of Fundamental Commissioning Agent

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Ilana Judah  on 

We are working on a project that is now under construction. Fundamental Commissioning was started by one party, with Enhanced Commissioning being undertaken by a second party.

4
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Fri Nov 11, 2022, 4:01 pm

Fundamental Commissioning of On-Site Solar Array

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Rachel Williams  on 

I am working on a project that, through a series of contract issues during construction, does not have commissioning documents for the PV array.

2
Principal
Hellmuth & Bicknese Architects
LEEDuser Premium Member
20 thumbs up
Wed May 11, 2022, 6:17 pm

CxA Qualification requirements

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Ryan Younis  on 

Hello, 
i am looking to see if LEED requires any credentials specifically for the CxA like a certified commissioning professional or PE?

2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Fri Feb 28, 2020, 9:06 pm

All equipment tested as part of commissioning?

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Jill Watkins  on 

I am LEED consultant on a convention center renovation/addition and some team members are asking whether or not all equipment needs to be tested in all modes of operation, or if one of each ty

3
President
AGR Consulting, LLC
LEEDuser Basic Member
14 thumbs up
Mon Aug 5, 2019, 5:47 pm

Commissioning of Existing Equipment

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Jatuwat Varodompun  on 

We have a major renovation project which is 40% of gross area. Do we need to commissioning the equipment of existing equipment of the rest 60%.

1
Sun Aug 11, 2019, 9:37 pm

Renewable Energy unable to be commissioned due to delays, can we still submit for LEED review?

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Rachel Manoguerra  on 

The project I am working on is "complete" and the owner wants to submit for final LEED review.  However, the PV has been delayed and not installed on the project.

3
Sat May 25, 2019, 4:37 am

Commissioning Documentation for 7 separate towers sharing a common ground floor & podium level with shared/mixed MEP Systems

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Joshua ADY  on 

We are working as an independent commissioning authority (ICA) for a LEED V3 registered project with the following configuration;

1
Sun Aug 11, 2019, 10:23 pm

OPR and BOD documents

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Carlos Vazquez  on 

I accepted an assignment of commissioning a 3,400 sq-ft project to apply for a LEED certification. I came in late in the game.

5
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Wed Oct 24, 2018, 8:17 pm