Equipments to be Commissioned for Fundamental Commissioning
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Daisuke Miura on
Hi, I have a question regarding the scope of equipments to be commissioned for Fundamental Commissioning.
Performing Commissioning Activities 3 years after occupancy
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Gaston Viau on
Hi!
Our NC-2009 project it's a 16,000sqf office building located in California.
Change of Fundamental Commissioning Agent
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Ilana Judah on
We are working on a project that is now under construction. Fundamental Commissioning was started by one party, with Enhanced Commissioning being undertaken by a second party.
Fundamental Commissioning of On-Site Solar Array
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Rachel Williams on
I am working on a project that, through a series of contract issues during construction, does not have commissioning documents for the PV array.
CxA Qualification requirements
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Ryan Younis on
Hello,
i am looking to see if LEED requires any credentials specifically for the CxA like a certified commissioning professional or PE?
All equipment tested as part of commissioning?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Jill Watkins on
I am LEED consultant on a convention center renovation/addition and some team members are asking whether or not all equipment needs to be tested in all modes of operation, or if one of each ty
Commissioning of Existing Equipment
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Jatuwat Varodompun on
We have a major renovation project which is 40% of gross area. Do we need to commissioning the equipment of existing equipment of the rest 60%.
Renewable Energy unable to be commissioned due to delays, can we still submit for LEED review?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Rachel Manoguerra on
The project I am working on is "complete" and the owner wants to submit for final LEED review. However, the PV has been delayed and not installed on the project.
Commissioning Documentation for 7 separate towers sharing a common ground floor & podium level with shared/mixed MEP Systems
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Joshua ADY on
We are working as an independent commissioning authority (ICA) for a LEED V3 registered project with the following configuration;
OPR and BOD documents
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Carlos Vazquez on
I accepted an assignment of commissioning a 3,400 sq-ft project to apply for a LEED certification. I came in late in the game.