Are all project parking spaces to be included in the count for an Addition, or just the new spaces designed for the Addition?

NC-v4.1 LTc8:Electric Vehicles
posted by  Mollie O'Rourke  on 

We have a project with a 4-story horizontal addition being added (it is actually a healthcare facility, but there are not currently any Q/A's in the HC Forum).  Being helathcare, there is a la

3
Sustainability Consultant
Stantec
LEEDuser Premium Member
25 thumbs up
Tue Apr 12, 2022, 4:34 pm

Project with no parking

NC-v4.1 LTc8:Electric Vehicles
posted by  Summer Gorder  on 

Can you still earn this credit with a project with no parking?

1
Mon Feb 28, 2022, 1:33 pm

electric vehicles and reduced parking footprint?

NC-v4.1 LTc8:Electric Vehicles
posted by  Craig Flandermeyer  on 

Is there a way in v4.1 to use these two credits in tandem?  V4 has some guidance that increases percentages if both are used.  Curious if anyone has attempted both.

1
Wed Mar 23, 2022, 5:53 pm

Electric Vehicle -required project documentation

NC-v4.1 LTc8:Electric Vehicles
posted by  Michelle DeLora  on 

I have a client asking me about Option 2 - which is ESVE ready for 10% of parking. In the online summary of the credit it does not go into the required uploads.

1
Mon Feb 14, 2022, 7:21 pm

Signage for EV spaces

NC-v4.1 LTc8:Electric Vehicles
posted by  Amanda Polematidis  on 

For those of you who completed the credit, would one sign for an area with EV charging stations suffice, or does each charging station need a sign?

2
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Mon Dec 6, 2021, 6:08 pm

Option 1: 2% or 5%, Option 2: 6% or 10%?

NC-v4.1 LTc8:Electric Vehicles
posted by  Timothy Ian Middleton  on 

Thanks to LEED User I just discovered the latest version of NC4.1_LTc8 requires 5% of spaces to comply with Electric Vehicle Charging Requirements, instead of 2%.

6
Mon Sep 27, 2021, 6:56 am

Level 1 EV chargers - any credit for extensive installations vs a few Level 2's?

NC-v4.1 LTc8:Electric Vehicles
posted by  Pooja Sannamani  on 

Does anyone have any experience in getting credit for more Level 1 chargers?  Increasing having clients question whether Level 2 is the right approach for mass rollout due to electrical infras

1
Fri Sep 17, 2021, 3:40 pm
1
Thu Aug 19, 2021, 1:12 pm

EV spaces for residential portion?

NC-v4.1 LTc8:Electric Vehicles
posted by  MARLOES REININK  on 

We have a mixed-use project (office, hotel, & residential apartments). With this credit now specific to EV spaces only, how are the residential occupant spaces addressed?

1
Tue Jul 6, 2021, 4:12 pm

EV charging for spillover parking

NC-v4.1 LTc8:Electric Vehicles
posted by  Deborah Lucking  on 

Our project has allocated areas for spillover parking (used a few times a year) in ones and twos around the site, accessible from an alley. much like on-street parking.

1
Tue May 4, 2021, 7:31 pm