Cafeteria with patio seating

NC-v4 EQc1:Enhanced indoor air quality strategies
posted by  Margaret Montgomery  on 

In a cafeteria situation where indoor seating bleeds into patio seating with operable windows and person doors between, I assume we still need a walkoff system?

4
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Tue Nov 1, 2022, 5:19 pm

Area behind fiberglass enclosure IF WALLBOARD IS INSTALLED

Homes-v4 MRp2:Durability management
posted by  Marijana Misic  on 

With fiberglass tub surrounds, the flanges are typically attached to the studs, and moisture-resistant wall finish is overlapped above and sealed.

1
Sun May 14, 2023, 6:20 pm

Translucent fixture for strategy D

NC-v4 EQc6:Interior lighting
posted by  Omar Elrawy  on 

IF I have a lighting fixture with direct light, however, the fixture's glass is translucent / white glass. i.e.

6
Architect - Cx Provider - Building Performance Specialist
GLHN Architects & Engineers
LEEDuser Premium Member
25 thumbs up
Thu Oct 27, 2022, 7:05 pm
1
Thu Oct 27, 2022, 3:03 pm

MRc3 Sourcing of Raw Materials - purchase of reclaimed brick

NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials
posted by  chuck merritt  on 

We are currently sourcing materials for the exterior space of our project and were trying to figure out if locally reclaimed belgian blocks would be applicable to the MRc3 Sourcing of Raw Mate

0

Envelope commissioning report

NC-v4 EAc1:Enhanced commissioning
posted by  Diana Giraldo  on 

We have aproject that had envelope comissioning inspecton done, are there any samples of a report or any guidance for the consultant that completed the inspection?

4
Architect - Cx Provider - Building Performance Specialist
GLHN Architects & Engineers
LEEDuser Premium Member
25 thumbs up
Tue Oct 25, 2022, 4:36 pm