50% of Receptable Controls to meet the Prerequisite

NC-v4 EAp2:Minimum energy performance
posted by  Kritika Kharbanda  on 

We are working on a project where it was missed during equipment procurement that open office furniture is required to have 50% of the receptacles controlled to meet the prerequisite under 90.1-201

1
Senior Energy Wizard
TLC Engineering Solutions
LEEDuser Premium Member
44 thumbs up
Mon Apr 13, 2026, 11:55 pm

Comprehensive Composting

NC-v4 INc1:Innovation
posted by  Alma Evans  on 

Hi there, I registered the project I worked on in Austin, TX - Govalle Elementary School for the comprehensive composting pilot innovation point and I want to thank AISD for providing the requ

3
Mon Apr 13, 2026, 2:55 pm

Applicability of Rainwater Management Credit – Direct Discharge to Natural Stream

NC-v4 SSc4:Rainwater management
posted by  Ahmed Alyousef  on 

We are seeking clarification on the applicability of the Rainwater Management credit based on our current stormwater strategy.

0

Use High Priority Site as Innovation

CS-v4 LTc3:High priority site
posted by  Sara Johansson  on 

Hello, I have a CS v.2009 project and wish to use the High Priority v.4 credit as an innovation credit.

3
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Fri Apr 10, 2026, 5:50 pm
2
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Fri Apr 10, 2026, 5:46 pm

Battery room (Litium-ion)

Data-Centers-NC-v4 EQc1:Enhanced indoor air quality strategies
posted by  Suksan Yongwattananun  on 

Our data center project has had litium-ion battery rooms which the pollution from battery can't occur in normal operation because of the litium-ion battery type.

2
Senior Sustainability Engineer
Meinhardt PTE Singapore
LEEDuser Basic Member
0 thumbs up
Tue Apr 7, 2026, 2:11 am
3
Mon Mar 30, 2026, 12:22 pm

Warehouse development with multiple units

CS-v4 MPR2:Must use reasonable LEED boundaries
posted by  Santiago Avila  on 

Hi all,

I am preparing to register a warehouse project consisting of four adjoining units. While the units are physically connected, they are not internally linked.

0

The location of Recyclable Storage

CS-v4 MRp1:Storage and collection of recyclables
posted by  SOYOUNG CHO  on 

Hi everyone,

I have a question regarding the location of storage for recyclables under the LEED requirements.

1
Sustainability Consultant | Senior Project Manager
Re:Vision Architecture
LEEDuser Premium Member
10 thumbs up
Fri Mar 27, 2026, 5:30 pm

Composite Panels and TVOC Range

CI-v4 EQc2:Low-emitting materials
posted by  Kenneth Hart  on 

It is clear that LEED v4.0 requires composite wood products to comply with the Composite Wood Evaluation in Table 1.

0