Contact local utility representatives to discuss participation in future DR programs
NC-v4 EAc4:Demand responseposted by DAVE LI on
The local utility company did not provide a demand response plan.
Demand Response strategies
NC-v4 EAc4:Demand responseposted by Dave Hubka on
Hello,
Are there a list of demand response strategies that are not allowed by GBCI?
for example, could an onsite diesal generator be used during a demand event?
DES cooling load reduction
NC-v4 EAc4:Demand responseposted by Nuttanee Vongveeranonchai on
Dear all,
Demand response credit requirements vs. best practices under all conditions?
NC-v4 EAc4:Demand responseposted by Joanna Switzer on
In evaluating our Climate Zone 2A / cooling dominated project, it comes as no surprise that 3-7pm in August is the peak occurrence for the (currently) proposed design, with cooling a
Demand Response Program available but building can't meet requirements
NC-v4 EAc4:Demand responseposted by Jason Garvens on
Can a project still be eligible to apply for the single point for Case 2 if the project's utility does offer a DR program but the project doesn't sign up for it due to the requi
details on load reduction
NC-v4 EAc4:Demand responseposted by Jens Apel on
This project is in an area where no utility provider program is available yet. So preparing the system and a demand reduction plan would earn one point.
One point for infrastructure-only questions
NC-v4 EAc4:Demand responseposted by Chad Thurlow on
Hello
Critical Peak Pricing
NC-v4 EAc4:Demand responseposted by RDK E&S on
I'm wondering if enrolling in a critical peak pricing tariff would qualify for this credit.
LEED v4 Reference Guide and EA credits
NC-v4 EAc4:Demand responseposted by Ivan Romero on
The Quick Reference table on page 22 of the LEED v4 Reference Guide indicates "n/a" in all columns except Healthcare for the EA credits Demand Response, Renewable Energy, Enhanced Refrigerant Manag