Lead CxA Representative appointment; Delay causing concerns... Urgent solution required!
NC-v4 EAc1:Enhanced commissioningposted by Olawale Taiwo on
Background Consideration:
Does implementing MBCx remove the requirement for discrete OCx functional performance testing?
NC-v4 EAc1:Enhanced commissioningposted by Ilkka Mäkelä on
Hello,
If MBCx were to be implemented in a project, is the discrete functional performance testing and reporting part of OCx not required?
MBCx Plan as part of the Ongoing Cx Plan
NC-v4 EAc1:Enhanced commissioningposted by Francesco Passerini on
Can the MBCx Plan be presented as a part of the Ongoing Cx Plan?
Maintaining 3rd Party
NC-v4 EAc1:Enhanced commissioningposted by Brett Farbstein on
I have had success acting as the fundamental & enhanced CxA as an employee of the project architect as long as the design team included an outside MEP engineer in v2009.&nbs
LEED AP + Independent CxA
NC-v4 EAc1:Enhanced commissioningposted by Mike D on
If a team is appointed as LEED AP on a project, can they also act as the independent commissioning agent (the team has not design or construction contract)?
Multiple CxAs?
NC-v4 EAc1:Enhanced commissioningposted by LUCY WILLIAMS on
Have any project teams had success using two different commissioning agents from two different entities in order to perform commissioning services on their project? For example, can the
What is Required to become a CxA
NC-v4 EAc1:Enhanced commissioningposted by Lucas McGill on
Hello, I have a little experience with performing commissioning on mechanical and electrical systems in buildings, but never on a LEED project. I've read that:
Enhanced Commissioning with a DES
NC-v4 EAc1:Enhanced commissioningposted by Deborah Lucking on
All - looking for clarification to this para from the v4 BD+C Reference Manual (page 401):
NC Major renovation - Building Envelope Commissioning
NC-v4 EAc1:Enhanced commissioningposted by SAMY Chamy on
Dear Concern:-
Monitoring-based commissioning
NC-v4 EAc1:Enhanced commissioningposted by Paula Rantanen on
In our project building, we have many measurement points that do not measure energy consumption directly but the energy consumption can be reliably calculated from the tracked data and the building