Preferred Parking a must for EVSE vehicles ?
NC-v4 LTc8:Green vehiclesposted by deepak cherukumilli on
Is 2% of total parking spaces for EVSE vehicles required to be preferred parking or can be any parking spaces. Green Vehicles credit language doesnot mention about this.
Off-site charging station
NC-v4 LTc8:Green vehiclesposted by Kristina Pobre on
Client is developing a ha land. We are applying certification for only a small part of it (about 2%). The LEED-project has its own parking and a % of it is for green vehicles.
Green Vehicle permitting and parking enforcement
NC-v4 LTc8:Green vehiclesposted by Kristen Callori on
Page 128 of the v4 Reference Guide shows a picture of preferred parking signage that includes the words "Permit Required".
Fast charge
NC-v4 LTc8:Green vehiclesposted by Dionisio Franca on
On LEED 2009, I remember reading that using a charger that could half the charge time would be counted as 2 charge stations. Did this change for LEED v4?
Clarification on EVSE demand response requirements
NC-v4 LTc8:Green vehiclesposted by Patrice McVeigh on
Can you please clarify two points regarding e-car demand response (DR) - 1. Are we correct in understanding that LEED considers building DR programs as separate from e-car DR programs? 2.
Reduced truck idling
NC-v4 LTc8:Green vehiclesposted by Julia Otero on
In a warehouse to pursue option 2, which characteristics must have external connectors in terms of power and position acording to the loading docks? Thanks!
Warehouses & EV Charging stations on parking
NC-v4 LTc8:Green vehiclesposted by Charline SEYTIER on
Dear all, we are currently working on a LEED Warehouses project including also some offices and a parking area.
Public Garage
NC-v4 LTc8:Green vehiclesposted by Summer Gorder on
I am working on a public project downtown that does not have any designated parking.
EV Charging Stations
NC-v4 LTc8:Green vehiclesposted by Steven Wychorski on
There is a conflict with the Online form and the Reference guide/LEED Online. Both LEED Online and Reference guide clearly state that EV Charging stations must be 2% of total Parking spaces.
Project with no associated off-street parking
NC-v4 LTc8:Green vehiclesposted by Miriam Ramirez Baumgarten on
Hi! Could a project with no associated off-street parking achieve credit compliance by installing electrical vehicle supply equipment (EVSE) in a taxi station near the project and having signage i