CS-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
Hello, is exterior lighting on a roof (terrace) regulated by ASHRAE 90.1-2007? Or shall it be modelled in the same way (same power and same schedules) in the proposed and in the baseline mode
Polyvalent Chiller Efficiency
CS-2009 EAp2:Minimum Energy Performanceposted by Francisca Herrera on
Hi, I hope you can help me with my query.
In a project in process of certification LEED v2009, we are evaluating the efficiency of a polyvalent chiller.
Elevators with regenerative braking - EAp2 form
CS-2009 EAp2:Minimum Energy Performanceposted by Pamela Svetllana Santos Souza on
Hello, We are modelling for LEED C&S 2009. The project has 26 floor type of mixed-use offices. My question is about the Minimum Energy Perfomance credit form (EAp2).
Lighting Requirements for Hotel in Core and Shell
CS-2009 EAp2:Minimum Energy Performanceposted by Jorge Lopez de Obeso on
Hi everyone,
We are currently working with a mixed-use building which has offices, commerce and a hotel.
Baseline Ventilation Rate for Proposed design with DCV (not required under 6.4.3.9)
CS-2009 EAp2:Minimum Energy Performanceposted by Iqbal Khalilullah on
Dear Marcus,
I wish to ask you regarding the Baseline Ventilation rate.
Data Center - Baseline System and ACP
CS-2009 EAp2:Minimum Energy Performanceposted by Michael Wahjudi on
- Our development is having 767.47 sqm of supporting offices and 21,340.69 sqm of data center related area.
VAV boxes
CS-2009 EAp2:Minimum Energy Performanceposted by Rathnashree Bharadwaj on
We request for a clarification regarding mandating the tenant to use the VAV boxes in core and shell projects. In a core and shell project, we will not know what system the tenant will be using.
ENERGY MODELING
CS-2009 EAp2:Minimum Energy Performanceposted by RICARDO GUEMEZ DIAZ on
Hello, In Mexico City we have a one project that is integrated in two phases, the phase one start the construction phase in 2011 and the second phase will start the construction phase the next year
Lighting control in Tenant space
CS-2009 EAp2:Minimum Energy Performanceposted by Indochine Engineering VN on
Hi, I have an open office, restaurant, apartment for rent in the mixed use building project. Im confused with lighting control mandatory section 9.4 ASHRAE.