Temperature and Humidity Monitoring During Flush
CI-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Nancy Henderson on
Is it part of the requirement of this credit to monitor temperature and humidity in the space during the flush out - or is it sufficient to provide the temperature set points and calculate the resu
Question on Selecting IAQ Test Locations
CI-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Melissa Wrolstad on
I am working on a small ~6,500 sq. ft. LEED-CI office space.
IEQc3.2 VOC Testing
CI-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by mark morehouse on
I have a 191,000 sf nc school that will require 11 sample points.
Option 1: Full Flush-out Before Occupancy - Is there a Min. CF?
CI-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Michelle Bracewell-Musson on
With Option 1, Path 1, we are expected to flush-out 14,000 cf/sf of outdoor air at 60 degrees temp. and 60% humidity min. Is there a minimum ventilation rate as with Path 2 which is 0.30 cf/min.?
Is flush out possible in countries with high humidity?
CI-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Katherine Ann Resurreccion on
Hi, we would like to know if flush out is practicable in areas where high humidity is experienced whole year, say 70-85%. Should we cancel out option 1 already and go for option 2 (IAQ testing)?
IAQ Testing AFTER Occupancy?
CI-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by buddy pribish on
I am aware of the verbiage in the LEED reference guide for IAQ testing to be completed PRIOR to occupancy, but considering that the flushout method can be completed DURING occupancy, I was wonderin
IAQ testing in a continuously occupied office
CI-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Maggie Edelstein on
Our project is a government office that will be continuously occupied throughout the duration of construction.
Option 1 - Path 2
CI-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Nancy Henderson on
I just had a mechanical engineer point out that the partial flush-out option does not include the requirement to maintain 60 degree temperature and 60% humidity.
outdoor delivery rates in a naturally ventilated space
CI-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Vera Voropaeva on
After receiving the project's review we are asked to provide outdoor delivery rates.