Construction IAQ Management Plan—Before Occupancy
Filter by location
Forum
Topic
Replies
Recent

Temperature and Humidity Monitoring During Flush

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Nancy Henderson  on 

Is it part of the requirement of this credit to monitor temperature and humidity in the space during the flush out - or is it sufficient to provide the temperature set points and calculate the resu

2
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Tue Mar 13, 2018, 3:01 pm

IAQ testing in a continuously occupied office

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Maggie Edelstein  on 

Our project is a government office that will be continuously occupied throughout the duration of construction.

1
Tue Sep 3, 2013, 9:47 pm

Option 1 - Path 2

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Nancy Henderson  on 

I just had a mechanical engineer point out that the partial flush-out option does not include the requirement to maintain 60 degree temperature and 60% humidity.

1
Sat Jul 28, 2012, 1:07 am

outdoor delivery rates in a naturally ventilated space

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Vera Voropaeva  on 

After receiving the project's review we are asked to provide outdoor delivery rates.

1
Thu Mar 21, 2013, 7:39 pm

IAQ testing and furniture (new and used)

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Melissa Schwartz  on 

I have a four story project where we are doing IAQ testing in phases because of a tight schedule. All workstations and new furniture will be installed prior to the testing of each floor.

1
Tue Nov 22, 2011, 5:38 am

Building Flush - Filter Change?

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Brianne Smith  on 

Our project is pursuing Option 1 Path 2 - Flush During Early Occupancy. Do filters need to be replaced after the flush, or only after construction as part of IEQc3.1?

1
Tue Apr 5, 2016, 5:12 pm

Building Flush Out - Chilled Beams / Radiant Cooling

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Nandana Kumar  on 

We have couple of projects where the HVAC system is being served by Chilled Beams and Radiant Cooling.

1
Fri Jul 6, 2012, 3:34 pm
1
Mon Jan 10, 2011, 4:32 am

Number of IAQ Sampling Locations in Apartment Building?

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Bill Kilpatrick  on 

I would appreciate advice on the number of sampling locations needed for LEED Testing per IEQ Credit 3.2 Option 2 in mid-rise Apartment buildings. We follow the sampling rules for commercial build

1
Thu Mar 21, 2013, 7:32 pm

phased flushing for hospital project

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Ed Clark  on 

Due to phasing plan the contractor will need to run AHU prior to completion of another phase of the project.

1
Fri Oct 21, 2011, 5:29 pm