Due to phasing plan the contractor will need to run AHU prior to completion of another phase of the project. If the area under construction is completely isolated from the area that has the flush out can we phase the flush outs over time to accomodate construction schedule or should we go for option 2 for the flushout and do it once all of the building is complete.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Susan Walter
HDRLEEDuser Expert
1296 thumbs up
October 21, 2011 - 1:29 pm
Is your AHU serving both areas? Can you phase the flushing by AHU? Testing prior to occupancy is likely an easier route. Are they doing any testing for ICRA?