Cost of Electricity and Gas not availiableCI-v4 EAc2: Optimize Energy Performanceposted by Rajat Wadhwa on Mar 30, 2023, 5:25 pm
What can we do if the cost per unit for electricity and gas not availiable? Can we use the average values for that city? Last reply: Rajat Wadhwa, Mar 31, 2023, 11:16 am |
|
Post-industrial recycled content: Can off-spec or expired product count as recycled contentNC-v4.1 MRc3: Sourcing of Raw Materialsposted by Mickel Maal on Mar 30, 2023, 9:58 am
Hi, We are a building insulation product manufacturer and are developing a new polyurethane foam insulation product. We want to have... Last reply: Dave Hubka, Mar 30, 2023, 7:58 pm |
|
Carpooling/preferred parking req for mixed use buildings.ND-Plan-v4 NPDc5: Reduced parking footprintposted by Emily Smith on Mar 29, 2023, 10:35 am
I have a project that is questioning the 10% carpool/shared use vehicle spaces requirement for all non-residential and mixed use buildings. Our mixed use buildings take up a majority of the total... Last reply: Emily Smith, Mar 30, 2023, 1:20 pm |
|
Total Annual ConsumptionCI-v4 EAc3: Advanced Energy Meteringposted by Deborah Stadler on Jun 26, 2020, 7:54 am
Our CI project is not doing an energy model, but using the prescriptive method (AEDG). What is the acceptable way to determine the Total Annual Consumption to confirm uses above the 10% that... Last reply: Marcus Sheffer, Mar 30, 2023, 11:24 am |
|
Alternatives to whole building meter in a multifamilyNC-v4 EAp3: Building-level energy meteringposted by Camilo Velez on Nov 23, 2021, 3:53 pm
Good afternoon, we are working on a multifamily project (registered as NC), by default all of the apartments have their own energy meter, but there is no single master energy meter... Last reply: Marcus Sheffer, Mar 30, 2023, 9:33 am |
|
Modeling Exterior Envelope and ConstructionCI-v4 EAc2: Optimize Energy Performanceposted by Rajat Wadhwa on Mar 28, 2023, 2:38 pm
Hi, I am trying to model 10th floor in a 13 floor building, My question is should I make floor and roof as a void where there is no heat transfer between roof and floors, also for... Last reply: Rajat Wadhwa, Mar 29, 2023, 10:42 am |
|
Sustainability Lead positionHelp Wanted: LEED-related Jobsposted by Emily Purcell on Mar 29, 2023, 9:50 am
Hi LEED Users, I'm changing jobs & SCB is hiring for my current position: https://www.scb.com/position/sustainability-lead... |
|
Certification Process- Is there a time limit for preparing documetation after the preliminary Design ReviewLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Konstantina Kalliakoudi on Mar 28, 2023, 9:45 am
Hello, I have following question about the Certification process. For the project I am working on, we will choose split review. So, that means, that in the beginning we are... Last reply: Susan Di Giulio, Mar 28, 2023, 1:12 pm |
|
Steel Finishing Products and VOCsCI-v4 EQc2: Low-emitting materialsposted by Akos Brandecker on Mar 28, 2023, 12:22 pm
We are working on a number of projects where a large amount of internal metal staircases and other architectural steel elements need finishing and painting on site. These are generally 2 pack... Last reply: Michelle Rosenberger, Mar 28, 2023, 12:58 pm |
|
USGBC calculatorLEED v4.1 Discussion Forumposted by Emerson Alas on Oct 15, 2020, 11:28 am
The "Arc_Data_Template" is the same "USGBC Calculator" referred to in the reference guide? Last reply: Chuck Lohre, Mar 27, 2023, 4:10 pm |