Commissioning for overseas projects

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Natalie Tan on Jan 2, 2012, 4:04 pm

Hi, we have a small USGBC LEED-NC project (400m2) in Kuwait where the Owner wants us (LEED Consultancy firm in Canada) to hire a...

Last reply: Chris Ladner, Jan 11, 2012, 8:56 am

EA Pre-requ. #1

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Jason Dohl on Sep 4, 2009, 1:45 pm

I am gearing up to put a Design-Build team together for a 6000 SF commercial building and our goal is Silver. To achieve the pre-req, can our Commissioning Authority be an experienced Design-...

Last reply: Ameet AA, Jan 11, 2012, 5:48 am

Where to upload responses to Preliminary Review

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Liz Valdez on Jan 5, 2012, 5:06 pm

My project has gone through the preliminary review. We had a number of questions related to EAp2. The instructions from the reviewer were to create a .zip file with the original credit...

Last reply: Emily Catacchio, Jan 10, 2012, 8:25 pm

re: LEED Project Registration for Sports Facilities

General forums
posted by David Posada on Jan 10, 2012, 6:49 pm

This does sound like one project, and in past CIRs and reviews the...

we have a training ceter

General forums
posted by ola shunnar on Nov 22, 2011, 4:22 am

we have a training ceter building and would like to register it under the CI, and my question is on the MPR, form 2: there is two phrases in the form that make me confused, which are the a)...

Last reply: David Posada, Jan 10, 2012, 5:19 pm

Dear All, I am new on LEED

General forums
posted by Andre peixe on Jan 10, 2012, 3:35 pm

Dear All,

I am new on LEED language and I am using this very interesting forum to learn something (actually a lot!) about it.

I have a similar situation. In a site of 80,000 sqf (...

Last reply: David Posada, Jan 10, 2012, 4:59 pm

Calculating when only a certain % of male RR's have urinals.

NC-2009 WEp1: Water Use Reduction
posted by Rand Ekman on Nov 22, 2011, 6:31 pm

While the Water Use Reduction Additional Guidance document, (updated August 16, 2010), clearly address’ how to calculate total daily uses both with and without urinals. It does NOT address what...

Last reply: Jonathan Weiss, Jan 10, 2012, 4:43 pm

Re: Existing Building with an outbuilding addition

General forums
posted by David Posada on Jan 10, 2012, 4:39 pm

Chris,
From what you describe, it sounds like the two buildings are substantially similar. Since there aren't full time occupants in the storage and lab building, pursuing EB&OM for...

WeP1 for LEED CI

NC-2009 WEp1: Water Use Reduction
posted by Linda Delair on Dec 20, 2011, 1:52 pm

I have a cut sheet on a faucet the building owners want to use in the public lavatories in their 3,5000 sq. ft.dental building. They and their staff are the only tenants. The psi and the gpm...

Last reply: Jonathan Weiss, Jan 10, 2012, 4:36 pm

Developing the plan post-construction

NC-2009 EAc5: Measurement and Verification
posted by Maura Adams on Jan 10, 2012, 3:51 pm

Is there any reason that we couldn't develop an M&V plan post-construction, assuming we have the necessary controls in place?