Topic | Recent |
---|---|
Mechanical Equipment- Alternative compliance pathSchools-2009 IEQp3: Minimum Acoustical Performanceposted by Marcio Alberto Casado Pereira on May 9, 2011, 12:00 pm
We are currently working on a project wich the HVAC system selected was the split highwall, and there are 3 evaporation machines inside each classroom. The measurement taken inside the classroom... Last reply: Marcio Alberto Casado Pereira, May 30, 2011, 10:16 am |
|
Design Submittal- To do or not to do?General forumsposted by Shannon Deeb on Apr 30, 2011, 12:19 pmthat are found in the BD&C Reference Guide Appendix 1. For energy modeling of those spaces see Appendix 2, and also the NC and CS 2009 EAp2 forums- there are some related comments there. Log in or register... Last reply: Shannon Deeb, May 30, 2011, 10:02 am |
|
When to submit documentationNC-2009 IDc2: LEED Accredited Professionalposted by javier bolanos zeledon on Feb 15, 2011, 8:10 pm
I didn't know where to put this question. I would like to know when is the deadline for submitting documentation. I'm participating in a small office building job that will take just 4 months for... Last reply: javier bolanos zeledon, May 28, 2011, 8:23 pm |
|
LEED Certifying a Building with an EnergyStar labelEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Dawn Brenner on Apr 7, 2011, 12:27 pm
The downton high-rise I am attempting LEED certification has an EnergyStar label that just expired on Mar 31, 2011. They would like EnergyStar recertification as soon as possible and attempt... Last reply: Michael Opitz, May 27, 2011, 5:52 pm |
|
Warehouse Classification QuestionEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Maria Unruh on Apr 13, 2011, 3:13 pm
I am working on a pharmaceutical storage warehouse that maintains over 300,000 SF of warehouse space at 72 degF year round due to gov't regulations. We thought this was a specialized case and... Last reply: Michael Opitz, May 27, 2011, 5:35 pm |
|
Re: Documentation Time for CreditsGeneral forumsposted by David Posada on May 27, 2011, 5:30 pm
I've not seen a breakdown by credit, as it can vary widely by the strategy pursued and experience of the team, but there's a related discussion of this question over at |
|
Number of facilities for transportation centerCS-2009 SSc4.2: Alternative transportation - bicycle storage and changing roomsposted by Robert Phinney on May 27, 2011, 9:12 am
We are renovating (to LEED CS V3) a train/bus station and cannot determine how to equate the number of bike racks for the project. It would appear that the shower/changing room numbers are to be... Last reply: Tristan Roberts, May 27, 2011, 3:59 pm |
|
No Fixtures Installed in Core & Shell ScopeCS-2009 WEp1: Water Use Reductionposted by Lauren Ulmer on May 20, 2011, 11:09 am
From what I have read on this website, my understanding is that if we are not installing any plumbing fixtures as part of the Core & Shell work, then we must make the water reduction a... Last reply: Curt Pascoe, May 27, 2011, 2:53 pm |
|
Definition of EntrancesEBOM-2009 IEQp2: Environmental Tobacco Smoke (ETS) Controlposted by Emma Sanborn on May 9, 2011, 6:26 pm
My question is whether an inoperative door qualifies as an entry, and thus needs a 7.5 m buffer area. My project site holds large events and needs to create a temporary fenced smoking area to... Last reply: Emma Sanborn, May 27, 2011, 1:23 pm |
|
EAp2 CaGBC CalculatorEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Emma Sanborn on May 16, 2011, 4:45 pm
I am working on achieving LEED for a convention centre in Canada. Since the facility type falls under "Other - Entertainment/Culture", we are required to use Option C3 (Energy Baseline Including... Last reply: Emma Sanborn, May 27, 2011, 1:15 pm |