FAQs about EAp2 :

We have installed submeters on our building but the utility bill includes energy use from several other buildings located on the same campus. How do we reconcile this during the LEED review process?

When is it possible to exclude up to 10% of the building from EAp2?

What do I do if the number of building occupants, operating hours, or vacant space changes during the performance period?

If you pursue the streamlined path for an Energy Star label, should the performance period for EAc6 match the 12-month time frame of the label?

How do I account for computers with multiple monitors on Portfolio Manager?

How should I treat vacant space on Portfolio Manager?

Our building includes a large laboratory space. Can our project benchmark under the Labs21 program?

We have an international project and the space type is eligible for an Energy Star rating. Can we pursue Case 1 to demonstrate compliance given the recently released alternative compliance paths for international projects?

We have a number of buildings on a single campus that we would like to certify at the same time. Is it possible to benchmark the buildings at the campus level?

I have a mixed-use building and am wondering if it is possible to pursue the prerequisite through Case 1. How do we proceed?

We have a building that consists of two attached structures and it’s unclear if we have to consider it a single building or if it should be certified as two separate buildings and benchmarked accordingly. How should we proceed?

How long is an Energy Star label valid to use with a streamlined approach for Case 1?

Our building includes heavy process loads that significantly increase the overall energy use in the building. If we submeter these loads, can we exclude this energy use for benchmarking purposes?

View answers »

Forum discussion

EBOM-2009 EAp2:Minimum Energy Efficiency Performance

EAp2 CaGBC Calculator

I am working on achieving LEED for a convention centre in Canada. Since the facility type falls under "Other - Entertainment/Culture", we are required to use Option C3 (Energy Baseline Including Historical Data plus Comparable Buildings). My first question revolves around the comparable data I am using. All of the energy consumption data is from 2008 (the most recent year we could consistently acquire from other convention centres across Canada). Is it okay to use this information from over two years ago, or does it need to be more recent? My second question has to do with the calculator itself. The macro in the program does not seem to be working properly as the information I am inputting in Table 8 is not transferring to Table 9. A red note on Table 9 states that there is "Data Missing from Table 8". To the best of my knowledge, I have input all of the relevant information. Is there any chance the file from CaGBC is not working correctly? If anybody can shed any light on this for me, it would be greatly appreciated!

3

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 05/17/2011 - 12:38

The historical energy use data of the project building can include three years of consecutive data within the previous six years of the start of the performance period. Energy use data from three comparable buildings must inculde two consecutive years. To normalize your building's historical data with comparable buildings I would use similar years for both. For example, use 2006, 2007 & 2008 energy data from your building + 2007 & 2008 from three comparable buildings to create a baseline. Also, LEED Online only asks for one year of energy use data from comparable buildings even though the LEED reference guide asks project teams to gather 2 years of data. Don't know what's going on with the online calculator.

Fri, 05/27/2011 - 17:15

Thanks for your response David. I should have clarified that we are doing the CaGBC version of LEED EB:O&M, so we don't have an online calculator, we have an offline excel calculator that's pretty buggy and causing some headaches. We'll continue to wait for CaGBC's answer on that though.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.