Pool Cover and Air souce heat pumpNC-2009 EAp2: Minimum Energy Performanceposted by Arub Vijay on Jan 10, 2012, 3:55 am
Can the mandatory requirement of swimming pool cover be exempted if an air-souce heat pump is used for pool heating? The pool is heated to 30 ºC, is the pool cover mandatory in this case... Last reply: Marcus Sheffer, Jan 10, 2012, 10:01 am |
|
Pavement Markings for Designating Preffered ParkingNC-2009 SSc4.3: Alternative transportation - low-emitting and fuel-efficient vehiclesposted by Amy Bechard on May 6, 2010, 3:32 pm
The image above shows marking 'LEED' on the pavement to designate preferred parking, is this standard practice or are there other designations that people have used? Last reply: Maura Adams, Jan 10, 2012, 9:24 am |
|
Patient Rooms and Thermal Comfort ControlsLEED for Healthcare forumposted by Susan Walter on Nov 29, 2011, 5:05 pm
I've always counted the patient rooms as individual spaces, not shared spaces, and have provided a single T stat. Yet, we have separate light controls for the nurses, patient and family areas... Last reply: Susan Walter, Jan 9, 2012, 4:29 pm |
|
Can recycled content and reg. mat be considered campus credits?LEED Guidance for Campuses and Multiple Buildingsposted by Cheryl Burkinshaw on Jan 5, 2012, 12:31 pm
Hi, We're currently seeking certification for a combined high school/ middle school new construction/ renovation project that are registered as separate LEED projects but within one campus LEED... Last reply: Elizabeth Thompson, Jan 9, 2012, 3:50 pm |
|
LEED EBOM for Industrial Building?LEED Rating System Selectionposted by Omer Moltay on Jan 2, 2012, 11:11 amneed to investigate the specific forums for the EB credits. Log in or register to post comments ... Last reply: David Posada, Jan 9, 2012, 1:13 pm |
|
What Rating System Should I Use?LEED Rating System Selectionposted by Kevin Griesemer on Jan 9, 2012, 12:23 pm
My client has an existing 500,000 sf warehouse... Last reply: David Posada, Jan 9, 2012, 12:54 pm |
|
Vestibules for conditioned buildingsCS-2009 EAp2: Minimum Energy Performanceposted by Julio Alvarado on Jan 7, 2012, 12:07 am
We have a CS project, climatized, on which the client is insisting we should not have entrance vestibules, which to my understanding is mandatory under ASHRAE 90.1. Are there any acceptable... Last reply: Marcus Sheffer, Jan 9, 2012, 11:46 am |
|
LEED boundary and Major AdditionsNC-2009 EAp2: Minimum Energy Performanceposted by Len Sciarra on Jan 7, 2012, 11:50 pm
A new project, under LEED-NC, is a major addition to an existing building, in this case a manufacturing facility which will result in basically three sections New Office, Existing Office, and... Last reply: Marcus Sheffer, Jan 9, 2012, 10:00 am |
|
Core and Shell- extent of building questionLEED Rating System Selectionposted by Krista Raines on Oct 25, 2011, 9:43 am
We are designing an office tower that is going for LEED Core and Shell certification. Under a separate contract we are doing a small portion of the interior fit-out (less than 40%) at the same... Last reply: Susann Geithner, Jan 6, 2012, 3:19 pm |
|
Pilot Credit 12 vs. CI- SSc3, Option 1, Exemplary PerformancePilot-Credits PC12: Reduced Automobile Dependenceposted by Simon Sue on Jul 18, 2011, 6:39 am
The requirements for Pilot Credit 12 appear to be precariously similar to the requiements for LEED 2009 CI SSc3 Option 1, Exemplary Performance. There is slight variation - for example:... Last reply: Chris Marshall, Jan 6, 2012, 3:00 pm |