Building occupied intermittently and use of Motion SensorsNC-2009 EAp2: Minimum Energy Performanceposted by Brooks Critchfield on May 31, 2011, 5:19 pm
We have a 3,000 SF building which will be occupied intermittently by the client/owner. One small part of the building is being continuously maintained at occupied temperatures, a second... Last reply: Marcus Sheffer, Sep 19, 2011, 12:08 pm |
|
Construction Details in Baseline ModelNC-2009 EAp2: Minimum Energy Performanceposted by Xing Shi on May 31, 2011, 11:51 am
In ASHRAE90.1-2007, the construction type and U value of Baseline Model is regulated. We use EnergyPlus to do energy modeling, so there is a problem, where can we find standard construction... Last reply: Marcus Sheffer, Sep 19, 2011, 12:06 pm |
|
case 2. Residential and Hospital Projects Only- RequirementsNC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Controlposted by Veronika Sundberg on Jun 14, 2011, 5:29 am
Hi, I have a question regarding case 2. Residential and Hospital Projects Only. In the requirement for the prerequiset 8 bullets are listed that needs to be met. The four first ones are... Last reply: Veronika Sundberg, Sep 19, 2011, 5:12 am |
|
Warehouse ClassificationEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Prudence Ferreira on Jul 21, 2011, 3:55 pm
We are trying to classify a winery. One of the areas is used for barrel fermentation, and is temperature controlled anywhere from 55-75 degrees based on the fermentation process. Would this... Last reply: Jenny Carney, Sep 16, 2011, 3:33 pm |
|
Energy Bills are the Entire Site and Not Broken Down by BuildingEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Cynthia Fowler on Aug 9, 2011, 2:39 pm
My project building is one of 40+ on a company's campus/site. They do not purchase electricity on a building-by-building basis, but for the entire site. My project building is metered and the... Last reply: Jenny Carney, Sep 16, 2011, 3:30 pm |
|
Added $$ for Pre-Reqs in PF CategoryGeneral forumsposted by Julie Hendricks on Sep 11, 2011, 9:04 pm
Overall, the prerequisites in this category are going to add significant cost to a base LEED certification over LEED 2009. I'd like to hear from... Last reply: Scott Bowman, Sep 16, 2011, 9:23 am |
|
countertops CSI classificationNC-2009 MRc4: Recycled Contentposted by Annette Bellafiore on Mar 9, 2010, 4:55 pm
The guidelines for MRc3 - 7 indicate that only items in Division 3 - 10, 31 and 32 should be included in the calculations unless you want to include all furniture. However, it seems like... Last reply: Benjie Herrera, Sep 16, 2011, 7:50 am |
|
MR Credit- Environmentally Preferable Structure and EnclosureGeneral forumsposted by Keith Lindemulder on Sep 13, 2011, 5:13 pm
First - PLEASE bring back some kind of number system like MR4, MR5, whatever...these credit names are too difficult to remember and differentiate. Case in point, under Option 2 of the... Last reply: Keith Lindemulder, Sep 15, 2011, 3:35 pm |
|
Looking for an exampleNC-2009 IEQc8.1: Daylight and views - daylightposted by Eamon Geary on Sep 8, 2011, 2:49 pm
In the course of the 30+ LEED projects I have participated in, I have never successfully achieved this credit. Recently, an internal group has been working together to figure out what we can... Last reply: Eddy Santosa, Sep 15, 2011, 12:17 pm |
|
Transient Occupants (specifically students)EBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Ashley Chiang on Aug 8, 2011, 7:04 pm