SF6 in MV switchgears- Any LEED limits?NC-2009 EAc4: Enhanced Refrigerant Managementposted by Werner Sobek on Feb 4, 2011, 6:49 am
Does the SF6 (Sulphur Hexafluoride) insulating gas used to quench the arc in electrical power equipment (MV switchgears) need to be taken into consideration under the EAc4? The credit language... Last reply: Tristan Roberts, Feb 18, 2012, 12:28 am |
|
Blower door test formNC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Controlposted by Stefania Minotti on Nov 22, 2011, 5:31 pm
Hi, does anyone know where I can find the ‘’Certificate of Field Verification and Diagnostic Testing’’ that needs to be filled out for each blower door test that is performed, as indicated in ‘’... Last reply: Tristan Roberts, Feb 17, 2012, 10:27 pm |
|
Electric CigarettesNC-2009 IEQp2: Environmental Tobacco Smoke (ETS) Controlposted by Andreas M. Roessler on Jan 31, 2012, 12:58 pm
Dear all, one of our major clients set an interesting question concerning electronic cigarettes. In the building - we already certified - smoking is not allowed, but could be electronic... Last reply: Tristan Roberts, Feb 17, 2012, 10:20 pm |
|
Site contaminationSchools-2009 SSp2: Environmental Site Assessmentposted by Carol Vick on Feb 17, 2012, 4:15 pm
I have a LEED for Schools project where we have site contamination from an old gas station leaky storage tank. We have the ESA II report and are applying to the state for assistance in a program... Last reply: Larry Sims, Feb 17, 2012, 10:17 pm |
|
Integral color and LEED concrete tracking formNC-2009 MRc4: Recycled Contentposted by Wendelyn Bone on Jan 18, 2012, 2:55 pm
I have documentation from the project's concrete supplier that includes integral color together with cementitious materials. In this case, integral color contributes significantly towards both... Last reply: Tristan Roberts, Feb 17, 2012, 9:57 pm |
|
Innovation- Double Transit RidershipNC-2009 SSc4.2: Alternative transportation - bicycle storage and changing roomsposted by Alicia Freire on Feb 17, 2012, 6:40 am
My understanding was that the only way to achieve this credit was to develop a Comprehensive Transportation Management Plan; however, the form also shows the following option: Last reply: Tristan Roberts, Feb 17, 2012, 9:30 pm |
|
MERV 13 filters on fan coil unitsSchools-2009 IEQc5: Indoor Chemical and Pollutant Source Controlposted by james moler, p.e. on Jan 12, 2012, 8:11 pm
Numerous... Last reply: Dylan Connelly, Feb 17, 2012, 8:08 pm |
|
Recycling Areas DesignationNC-2009 MRp1: Storage and Collection of Recyclablesposted by Sunayana Jain on Feb 14, 2012, 8:21 am
In the floor plan, is it required to document the recycling areas as paper, corrugated cardboard, glass, plastics and metals specifically or just designating as recycled areas in floor plan will... Last reply: Emily Catacchio, Feb 17, 2012, 7:31 pm |
|
Can the existing roof count?EBOM-2009 SSc7.2: Heat island effect - roofposted by Kelly Wieczorek on Feb 16, 2012, 12:22 pm
If our existing roof meets the requirements can we achieve the credit, or does there have to be a change/upgrade from the existing to comply? Last reply: Emily Catacchio, Feb 17, 2012, 7:23 pm |
|
non-finished flooring for C&SCS-2009 IEQc4.3: Low-emitting materials - flooring systemsposted by Natalie Ng on Mar 29, 2011, 12:07 am
the project is an office building development, the project proponent would like to leave the feasiblity of installing carpet to the tenants thus the floor will be concrete finish with raised... Last reply: Lauren Sparandara, Feb 17, 2012, 7:12 pm |