Confidential Materials Cost BudgetCI-2009 MRc4: Recycled Contentposted by samala hartley on Mar 27, 2012, 6:34 pm
This LEED CI project would like to maintain privacy in regards to their materials budget. This conflicts with our need to compare construction cost and new material costs for such credits as “... Last reply: Emily Catacchio, Apr 10, 2012, 6:34 pm |
|
FSC wood, but not FSC shop. Buy FSC anyway?CI-2009 MRc7: Certified Woodposted by Valerie Molinski on Mar 27, 2012, 9:44 am
We are pursuing MRc7 on a project that I am working on, but the millwork shop does not have a COC certification. We should be able to achieve the credit anyway with the other... Last reply: Emily Catacchio, Apr 10, 2012, 6:32 pm |
|
MRp1: Storage and Collection of RecyclablesGeneral forumsposted by Sundararaj Subburaman on Dec 20, 2011, 9:47 amreccommend reposting this question under the MRp1 credit forum. I think you'll have a better time finding an answer there.Thank you! Log in or register to post comments ... Last reply: Emily Catacchio, Apr 10, 2012, 6:25 pm |
|
30% for all spaces individually or for the total?NC-2009 IEQc2: Increased Ventilationposted by Emmanuel Pauwels on Dec 2, 2011, 12:26 pm
We have an overall 30% ventilation above ASHRAE, but it is different in each spaces. Some spaces have 10% more and other have over 40% more. For credit compliance do we need 30% on the total... Last reply: Dylan Connelly, Apr 10, 2012, 4:43 pm |
|
LEED BoundaryGeneral forumsposted by Sherri von Wolfe on Apr 10, 2012, 4:40 pm
Good afternoon, |
|
Documentation of Roof- In GeneralEBOM-2009 SSc7.2: Heat island effect - roofposted by David Tetro on Apr 10, 2012, 1:23 pm
Hi all - just a question as I am new to this... Last reply: Ben Stanley, Apr 10, 2012, 3:49 pm |
|
Recycled Content Table Indicator IncompleteNC-2009 MRc4: Recycled Contentposted by Michael Esposito on Feb 10, 2012, 8:51 am
I have filled out all the information based on actual costs for all product materials and at the end of the form there are no documented points and the "table indicator" states "incomplete". Not... Last reply: Stacie Wilson, Apr 10, 2012, 2:06 pm |
|
FTEs or Residents for Mixed-use residential project?Calculating FTEsposted by Joel Cesare on Mar 13, 2012, 11:59 am
Our project is 4 floors: first floor with three commercial tenants and top 3 residential. The occupant numbers for the residential is straight-forward based on LEED default values. The tenants... Last reply: Emily Catacchio, Apr 10, 2012, 12:40 pm |
|
revised student numbers on form 3 not updating on templateSchools-2009 SSc4.2: Alternative transportation - bicycle storage and changing roomsposted by Joseph Bace on Feb 3, 2012, 1:19 pm
students above grade 3 # was corrected on form 3, template student # still shows old #.... Last reply: Emily Catacchio, Apr 10, 2012, 10:23 am |
|
Jasmin,General forumsposted by Emily Catacchio on Apr 10, 2012, 10:12 am
If the first building is entirely complete and is already certified under New Construction, then you will keep the certification even though there is further work happening which is outside of... |