Enhanced Commissioning and Measurement and Verification

NC-2009 EAc3:Enhanced Commissioning
posted by  Saju Varghese  on 

Hello, It been a little hard to draw the line between the enhanced commissioning scope and the measurement and verification scope.

3
Default Avatar
RLBA
LEEDuser Premium Member
1 thumbs up
Sat May 25, 2019, 4:25 am

D & C Team perform Commissioning, CxA only Verifies?

NC-2009 EAc3:Enhanced Commissioning
posted by  Adrian Arenas  on 

Our project is pursuing Enhanced Cx credit v2009.

0

Mid construction Review

NC-2009 EAc3:Enhanced Commissioning
posted by  Omar Elrawy  on 

I've received a reviewer's feedback stating that "the required back-check Design review occurred after the date for beginning of construction...Provide a narrative explaining the sequence

1
Mon Apr 23, 2018, 9:31 pm

Enhanced Commissioning in District energy Systems (DES) with Combined Heat and Power (CHP) plant

NC-2009 EAc3:Enhanced Commissioning
posted by  Ricardo Sá  on 

We are certifying a project that is being developed in a site that comprises a District Energy System based on a Combined Heating and Power Plant (DES-CHP).

0

Appointment of CxA for Enhanced Commissioning

NC-2009 EAc3:Enhanced Commissioning
posted by  kerry wang  on 

My project is about to complete the Design Development stage and CxA is to be on-board soon.

0

When is the building considered occupied?

NC-2009 EAc3:Enhanced Commissioning
posted by  Lise Dannesboe  on 

Hi. For the 10 month post-occupancy commissioning - when is the post-occupancy considered started. When all occupants (100%) have moved into the house and all equipment is up and running?

1
Tue Dec 5, 2017, 6:56 pm

UPS system need to be commissioned?

NC-2009 EAc3:Enhanced Commissioning
posted by  Eric JS   on 

Hi all, UPS system is used as a back up power in case if there is power failure. In that case. UPS itself consume small amount of power.

1
Sun Jan 30, 2011, 8:09 pm

Can we go for enhanced commissioning after start of operation

NC-2009 EAc3:Enhanced Commissioning
posted by  Abdulrahman Sherazy  on 

Our client have decided suddenly to go for enhanced commissioning. The construction is complete and the building starts to operate. The fundamental commissioning has been already done.

1
Tue Jun 11, 2013, 6:17 pm