CHP Electric Output
NC-2009 EAc1:Optimize Energy Performanceposted by Francesco Passerini on
I have some doubts concerning Appendix D of the document “Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 – Design & Construction” http://www.usgbc.org/ShowFile.aspx?Doc
Exterior lighting artwork - Process Load
NC-2009 EAc1:Optimize Energy Performanceposted by Victoria Watson on
Hi, I am working on a project where they are proposing a lighting installation forming a piece of artwork. They are asking whether it can be excluded from the LEED calcs.
Major Renvation Baseline Building Envelope Selection for Title 2
NC-2009 EAc1:Optimize Energy Performanceposted by Jayme Buresh on
Hi, I know that Appendix G states that if the envelope of a building is renovated, then the existing envelope construction is used for the baseline.
Car Park Ventilation Fan Energy Savings
NC-2009 EAc1:Optimize Energy Performanceposted by Chilufya Lombe on
Hi, on a recent project we were requested to provide evidence that 5 buildings built within the last three years did not have carbon monoxide sensors installed in the basement car parks in order to
District Thermal Energy Savings
NC-2009 EAc1:Optimize Energy Performanceposted by Matthew Higgins on
Does anyone have experience with district thermal energy by means of a central condenser water loop?
Basecase System selection
NC-2009 EAc1:Optimize Energy Performanceposted by SAMY Chamy on
Dear All:- Our project is G+3 factory building and a floor area of 1,80,000 Sq.ft 80000 Sq.ft is A/c area and remaining areas are Ventilated by fresh air fans so we take system 06-System 6—Pack
Comparing Process Pumping between Baseline and Proposed
NC-2009 EAc1:Optimize Energy Performanceposted by Evelyn Dicks, EI, CxA on
I am working on a lab building near the coast where seawater is pumped into the building for use by researchers.
Campus/District Geothermal Loop
NC-2009 EAc1:Optimize Energy Performanceposted by Aaron Cook on
Is there a guidance document/discussion available on how to treat a campus geothermal loop (servicing several buildings) that provides the working fluid to the LEED project building conditioned wit
How to model chiller for only one wing of an existing building
NC-2009 EAc1:Optimize Energy Performanceposted by Allison McSherry on
I am currently working on a LEED v3.0 model in trace 700. It is a historic building originally built in the late 1800s. It has a variety of unique situations that I am unsure of how to model.