Forum quick links
Overall Feedback on Pilot Credit
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Kavita Karmarkar on
As our project is located in Northern CA, it is not diffidult to achieve this credit as there are many haulers with third-party certified diversion rates (RCI) in the area.
PC MRpc87 Feedback
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Dan Ackerstein on
Feedback from the architecture firm and general contractors re: PC implementation in Southern California
State Verification Program
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Vanessa Hostick on
Has anyone tried submitting with a state led auditing and verification program? The credit criteria state rates and facilities must be reveiwed by a "qualified third-party organization"
Averaging Facility Rates over Time
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Vanessa Hostick on
The credit guidance notes that to apply rates over time, a project's waste should be the weighted average for the facility over the time in which the project sent materials to the facility.
100% of waste or most of waste?
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Allison Smith on
Has anyone had sucess achiving this credit by using an RCI facility for the majority of the waste and then using another facility for the demolition waste?
Pilot Credit 87- Verified Construction and Demolition Rates
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Brightworks Sustainability on
This credit was fairly easy to meet but I am wondering if all the C&D processing facilites we used must be verified?
MRpc87 Available Facilities
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Michelle Rosenberger on
There are still very few facilities certified under RCI. Projects that have pursued this pilot have all been proximate to the necessary receiving facilities and would have likely used them anyway.
Recycling Rates
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Stephanie Graham on
Under Credit-Specific Documentation it says, "Recycling rates applied to a project's waste generation must be the weighted average for the facility over the time in which the project sent materials
Documentation for multiple projects
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by swapnil patil on
I am pursuing this credit for multiple projects.
Pilot Credit 87 - Verified Construction and Demolition Rates
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Patty Lloyd on
Documentation of this credit was easy because we are using a hauler who has a CORR certified facility that is near to our job. We tried this pilot credit once before and did not achieve it be