Some projects fail the first round of testing, and have difficulty scheduling or budgeting for the required flush-out and re-testing. Those projects are, unfortunately, forced to give up on this credit.
If IAQ test samples exceed any of the maximum concentration levels, the space must be flushed out with an increased rate of outside air, as recommended by the testing agency, and re-sampled to confirm compliance before allowing occupants to move in.
Samples should be collected in the breathing zone—three to six feet above the floor—during hours when the building will normally be occupied. Record the exact locations in which samples are taken in case follow-up samples are required.
IAQ testing must occur prior to occupancy, but conditions should be as similar as possible to the air that occupants will breathe. Tests should be performed during normal operation of the building’s HVAC system, including normal daily start times.
IAQ testing requires at least one sample for every 25,000 ft2 in each portion of the building served by a separate ventilation system. Sampling locations should be in areas with the least ventilation and the greatest presumed potential for contaminant source strength.
The cost of IAQ testing varies widely depending on the number of tests needed for your project, the availability of local testing firms, and the type of test. Check your options early in order to factor this in, but plan to pay $500-$1,500 per testing location.
Extra attention must be paid to ensure strict adherence to the requirements for low-emitting materials (IEQc4) and the successful implementation of a construction