100002527

Edit the Intent to read as: "To support high-performance, cost-effective, equitable project outcomes through an early analysis of the interrelationships among systems."

100002494

Under Option 2, revise the first paragraph to read as follows:

Existing:
‘Adopt a Natural Resource Conservation and Restoration Plan within the last five years or develop one based on the study carried out under NS Prerequisite: Ecosystem Assessment to meet requirements for ANY three features of the ecosystems present within the city or community:’

100002495

Under Access to Transit Facilites, add a new footnote after "...or a pulse point..." that reads as:

"Pulse point is a transport node where multiple modes of transport may converge or pass through with each of them having a defined frequency and are coordinated with each other."

100002501

Under Solid Waste Management Plan, add a new footnote after "Provide a solid waste management plan" that reads as: "In lieu of a consolidated solid waste management plan, cities and communities may provide individual plans, ordinances, regulations, or policies to demonstrate compliance with the prerequisite requirements."

In the third bullet under Solid Waste Management, delete last sentence beginning with " In addition, all the organic waste..."

After the "AND" replace "Divert a minimum of 35%...." with:

100002486

SCHOOLS
Under HVAC Background noise, delete the second sentence: Follow the recommended methodologies and best practices for mechanical system noise control in ANSI Standard S12.60–2010, Part 1, Annex A.1.

HEALTHCARE
Under Option 1, speech privacy and sound isolation, first bullet, replace Section 1.2-5.1.6 with Section 1.2-6.1.5 and 1.2-5.1.6.2 with Section 1.2-6.1.6

Under Background noise, first bullet, replace Section 1.2-5.1.4 with Section 1.2-6.1.4

100002490

Under Option 1 and Path 1, delete both instances of "completed floor"
Under Path 1, revise last sentence to read as "Calculate reuse of the existing project area according to Table 1.

Revise Table 1 title to "Path 1 Points for reuse of existing building structural elements"
In Table 1, column 1 header, replace 'floor' with 'project'

Under Path 2, revise to read as "... for at least 30% of the entire completed building, including additions."