Topic

Flush out in climate zone 1

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Adi Negara, LEED AP BD+C on Sep 24, 2013, 5:52 am

Hi, does anyone here have ever implement flush out in a tropical climate area (climate zone 1 --> high temperature and humidity) and succeed obtaining this credit point?

and what flush...

Last reply: Dale Walsh, Oct 8, 2013, 2:16 am

Using option 1 phase flush out 14,000 cf of outdoor air per sf

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Benjie Herrera on Aug 25, 2013, 7:41 pm

If we use phase flush out , (1)phase 1 - delivery of out door air min. of 3,400 cf for 7 days pre occupancy and (2)phase 2 -remaining balance on 14,400 for 53 days during occupancy, when...

Last reply: Dylan Connelly, Sep 30, 2013, 8:11 pm

Apparatus Bay Flush out

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Richard Naldrett on Sep 18, 2013, 9:44 am

We have a Fire Station project scheduled for a flush out of the Appratus Bay. The space has heating but there is not a simple way to control humidity. Has there been any experiances with this...

Last reply: Michelle Rosenberger, Sep 18, 2013, 11:41 am

Flush out in tropical climate region (Climate Zone 1)

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Adi Negara, LEED AP BD+C on Aug 29, 2013, 6:15 am

Hello,

Our project is in Indonesia (...

4 PCH Testing and SBR Verification

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Tom Nichols on Jun 11, 2013, 8:19 am

Can anyone assist with the 4-PCH...

Last reply: Keerthi Ratnayake, Jul 23, 2013, 12:20 am

Flush Out Challenges

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Jamie Abernethy on Jun 6, 2013, 9:09 am

We had enough time (14days) built into the schedule to do a pre-occupancy flushout. However, days 10-12, which happened to fall on a weekend, we lost power to the whole building and the boilers...

Last reply: Dylan Connelly, Jun 10, 2013, 9:19 pm

Combination of Test and Flush

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Michael McVinney on May 29, 2013, 9:26 am

On a hangar project, there is a conditioned Admin space and an unconditioned Hangar space. The project team would like to flush the Admin and test the Hangar to avoid the cost and hassle of using...

Last reply: Dale Walsh, May 30, 2013, 2:11 am

Do non-regularly occupied spaces have to be air tested?

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by David Groseclose on Apr 11, 2013, 10:28 pm

Hello,
if you go for option 2, and conduct an air testing in a lab building, do you also need to do the testing in Non- Regularly occupied spaces, such as carpark, toilets, mechanical rooms...

Last reply: Dale Walsh, Apr 30, 2013, 10:24 pm

IAQ Testing- no lab

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by MARIO DE JESUS CARMONA VINAS on Mar 13, 2013, 12:20 pm

I have a project that will be conducting the Air Quality Testing. I own the equipment that uses the EPA method for all the contaminants LEED lists, but I will not be conducting the testing thru a...

Last reply: Dale Walsh, Apr 30, 2013, 10:04 pm

Multi Unit Residential Building- Phased Occupancy

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Erin Norton on Mar 28, 2013, 2:26 pm

I understand that in order to obtain this credit, 10% of the first 100 dwelling units and 5% of any additional units of the multi-unit residential building must be tested for the specified LEED...

Last reply: Michele Helou, Apr 19, 2013, 4:19 pm