Forum quick links
Lead Paint
Schools-2009 SSp2:Environmental Site Assessmentposted by Adam Musante on
Generally speaking, is the presence of lead paint in an existing school from the 1950's cause for concern and must be addressed or else the prerequisite is not satisfied?
Can I defer any ID credit to submit it w/ construction package ?
posted by Matt Dem on
Hi, I previously filed an innovation credit with my design preliminary submission and received an comment from GBCI therefore it is pending.
Where do I upload the response report for Design Final Package ?
posted by Matt Dem on
We, as a team are getting ready to submit our design final submission and prepared a report to respond to each individual comments made by GBCI.
Reclamation Land
ND-v2009 SLLp3:Wetland and water body conservationposted by WT Ho on
To stay "untouched" to water body, does it mean that a project with reclaimed portion is ineligible for ND, even if other potion of the future development land is previously developed? What if tha
Thermal Comfort Survey
NC-2009 IEQc7.2:Thermal Comfort—Verificationposted by Leed User on
I used the survey template provided on this site and was denied the credit saying it did not address all of the ASHRAE 55-2004 environmental variables (air speed, humidity, radiant temperature, and
Lease Agreement an option to comply with the credit requirements
CS-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Katherine Ann Resurreccion on
Hi, We are currently documenting the requirements for this credit and our option in order to comply is to provide a Tenant/Lease Agreement.
Process loads
NC-v4 EAc2:Optimize energy performanceposted by Ake Larsson on
In our company, we have introduced LEED as mandatory for all new construction projects.
How long do you have to do surveys?
NC-2009 IEQc7.2:Thermal Comfort—Verificationposted by Parker williams on
How long do you have to do surveys? Is this suppose to be ongoing forever?
EAp2-4: Energy Star equipment: conversion from kWa to Watts
CI-2009 EAp2:Minimum Energy Performanceposted by Sarah Simchuk on
I'm attempting to register the energy star equipment for my project under Table EAp2-4. The table asks for Rated Power in WATTS.