Case 2 Option 2?

CI-2009 SSc3.3:Alternative Transportation—Parking Availability
posted by  Gail Napell  on 

our client has far less than 75% of the building. the building has parking, but it is not allocated to any tenant and not subsidized. Please confirm this achieves NO points?

1
Sat Aug 26, 2017, 10:44 pm

Applicable Cooling source in Propose case - LEED Group - v4 C&S

CS-2009 EAp2:Minimum Energy Performance
posted by  Ashraf Ali Khan Khan  on 

I am modelling for LEED GROUP - v4 BD+C: CS. Project has 40 Office buildings shared with same basement and served with multiple Water Cooled Chillers as cooling source.

1
Fri Jun 9, 2017, 1:06 pm

LEED Group C&S - Applicable Cooling source in Propose case

CS-v4 EAp2:Minimum energy performance
posted by  Ashraf Ali Khan Khan  on 

I am modelling for LEED GROUP - v4 BD+C: CS. Project has 40 Office buildings shared with same basement and served with multiple Water Cooled Chillers as cooling source.

1
Fri Jun 9, 2017, 1:06 pm

Campus DES definition

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Luis Huertas  on 

While reading the definition in the District or Campus Guidance on what is a DES, it is not clear as whether one can consider each energy source an isolated DES or all the energy sources aggregate

1
Thu Jun 8, 2017, 8:33 pm

25% vegetated requirement and accesibility

NC-v4 SSc3:Open space
posted by  Mercè Llorca  on 

I've been wondering if when the credit ask for vegetated área, it would be enough to take the 25% from the 30% required área or, if the project has larger outdoor space than 30%, the requirement fo

1
Sun Aug 27, 2017, 8:35 pm

Core & Shell Retrofit

CS-v4 SSc1:Site assessment
posted by  Juliana Malho  on 

I'm wondering if the credit is achievable by retrofit projects.

1
Sat Aug 26, 2017, 4:38 pm

Baseline system selection

NC-2009 EAp2:Minimum Energy Performance
posted by  Madushan Samarakoon   on 

I am working with a data center project which have 3 floors but air conditioned area is less than 25000 sqft. But total area is exceeding 25000 sqft with unconditioned toilets and corridors.

1
Mon Jun 19, 2017, 4:40 pm

Lumens emitted at or 90 degrees from nadir

NC-2009 SSc8:Light Pollution Reduction
posted by  Anna Korinkova  on 

Hello, When calculating the number of lumens emitted at or above 90 degrees from nadir, is it possible to disregard the lumens that are shielded by the building its self / are not emmited directly

1
Mon Jun 12, 2017, 5:01 pm

Natural Ventilation

NC-2009 EAc4:Enhanced Refrigerant Management
posted by  SAMY Chamy  on 

Dear Concern:- Our project does not have any A/c spaces and Equipments So we dont use any Refrigerants so can we claim this credit Is there any CIR available for this situation Dut to the non u

1
Tue Jun 13, 2017, 7:59 am

PPA as renewable energy production?

CS-v4 EAc5:Renewable energy production
posted by  Lai-San wong  on 

Hi! In the requirement for EAc5 (BD+C) it is stated: "The use of solar gardens or community renewable energy systems is allowed if both of the following requirements are met.

1
Mon Aug 28, 2017, 1:41 pm