calculation of material cost

NC-2009 MRc5:Regional Materials
posted by  Doreen Kruschina  on 

Hi, in every LEED Project we do struggle in obtaining the material costs as many companies refuse to split their invoices in those for material and those for labour. Question is whether the assumpt

1
Mon Oct 20, 2014, 2:35 pm

Regularly Occupied Spaces

NC-2009 PIf3:Occupant and Usage Data
posted by  Lauren Bellamy  on 

Hi, I am working on a project under LEED BD+C that has some shell space that will no be outfitted until well after the completion of the construction and LEED documentation.

1
Wed Oct 15, 2014, 5:39 pm

Long Term Service Contract

NC-2009 EAc4:Enhanced Refrigerant Management
posted by  Erin Holdenried  on 

Does anybody have an example of a long term service contract, or know specifically what needs to be included in the contract in order for it to be accepted by the GBCI reviewer?

0

Pilot vs v4 Demand Response - Full Automation

Pilot-Credits EApc8:Demand response
posted by  Jennifer Wehling  on 

I have a LEED NC 2009 project that wants to use Demand Response as an Innovation Point.

0

Masonry Flash Mastic

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Chris Moore  on 

Our masonry contractor submitted VOC documentation on Wire-Bond Aqua Flash Mastic with a VOC content of 270 g/L. I am first not sure if this needs to be submitted for IEQc4.1 or not.

1
Mon Oct 20, 2014, 3:43 pm

How to calculate Squatter Toilet in we p1? and roof garden?

NC-2009 WEp1:Water Use Reduction—20% Reduction
posted by  Shenhao Li  on 

HI, i have 2 questions to ask: 1.Now i have a hotel project in china. In this project, Several squatter toilets(with water tank) are designed and will be constructed in the future.

1
Tue Oct 14, 2014, 12:42 pm

exceptions and alternative options for vestibules

NC-2009 EAp2:Minimum Energy Performance
posted by  Francesco Passerini  on 

According to 5.4.3.4 (mandatory provision) enclosed vestibules shall protect building entrances that separate the conditioned space from the exterior.

1
Wed Oct 15, 2014, 12:39 am

LEED V4 DATA CENTER

NC-2009 PIf1:Minimum Program Requirements
posted by  Caroline Vallieres  on 

There is a new data center extension to an existing building of a different use (office). The extension is accessible via a corridor. The buildings do share an electrical box.

1
Tue Oct 14, 2014, 11:29 pm

Electric consumption based on EAc1

NC-2009 EAc6:Green power
posted by  Lise Dannesboe  on 

The percentage of RECs is calculated as a percentage of the result of the energy model in EAc1. Does this include or exclude the amount of renewables on site.

1
Wed Oct 15, 2014, 12:42 am

Expansion areas

NC-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  Gustavo De las Heras Izquierdo  on 

Our LEED Project Boundary includes a future expansion area. This area has grown native species naturally. Can this vegetated area be counted towards this credit?

1
Mon Dec 8, 2014, 6:15 pm