CS-2009 EAc5.1:Measurement and verification - base buildingposted by Muhammad Faisal Azizullah Jaffar on
We are working on a mall project going ahead with the LEED CS GOLD.We are currently on tender stage and the client has suddently come up with the LEED requirement.
Case 2 Calculator - Space Types
EBOM-2009 EAc1:Optimize energy efficiency performanceposted by Timothy Casper on
Our project is a mixed use building used by community groups and has several different space types within it (theater, classrooms, event areas, kitchen, offices).
Projects outside the U.S.
EBOM-2009 WEp1:Minimum indoor plumbing fixture and fitting efficiencyposted by Stefanie Hoffmann on
Dear all, Having worked on a LEED EBOM project in Helsinki, Finland, where we were unfortunately not able to fulfill one of the prerequisites (EAp2), motivated me to dedicate my bachelor's thesis t
Projects outside the U.S.
EBOM-2009 EAp2:Minimum energy efficiency performanceposted by Stefanie Hoffmann on
Dear all, Having worked on a LEED EBOM project in Helsinki, Finland, where we were unfortunately not able to fulfill one of the prerequisites (EAp2), motivated me to dedicate my bachelor's thesis t
Temporary carpets / rugs
NC-2009 IEQc4.3:Low-emitting materials - flooring systemsposted by Maya Karkour on
Hello, Do roll-out carpets / rugs usually used in residential apartments need to be certified?
Planned Transfer Center
NC-2009 SSc4.1:Alternative transportation - public transportation accessposted by Josh Mauldin on
My project is a fire station that is the first project on the site of a mixed use development. A bus transfer center is planned to be built directly across from the fire station.
Section 1.4: Mechanical System Design Criteria
CI-2009 EAc1.3:Optimize energy performance - HVACposted by Nick Chiarelli on
If I could get some clarification on this section it would be a huge help! Total project space load (heating and cooling): Is this the sum of all seperate max space loads or is this the load of th
Crawl space included in GSF? Interior courtyards?
NC-2009 PIf2:Project Summary Detailsposted by Michael Wironen on
We have a fairly complicated building project that includes two areas that are unclear to me as to whether they should be included in the gross floor area calculation: 1.
Serving all occupants
NC-2009 SSc4.2:Alternative transportation - bicycle storage and changing roomsposted by Jennifer Benedict on
I am building a new tower right next to an old tower, connected by an existing parking garage. Our LEED boundary is just the new construction.
100% OA VAVs
CI-2009 IEQc1:Outdoor air delivery monitoringposted by Jeremy Kuhre on
We are remodeling two floors of a high-rise office tower. A 100% OA VAV introduces OA into the mechanical room for each floor where it is mixed with return air.