What can we claim?NC-2009 IDc1: Innovation in Designposted by Clare Parry on Oct 19, 2011, 7:37 pm
Hi all, Last reply: Becky Balsano, Nov 3, 2011, 12:54 pm |
|
MR Credits: What nothing on CSI Masterformat AlternativesGeneral forumsposted by Jean Marais on Oct 28, 2011, 2:12 am
In Germany we use the DIN 276, in the UK I think it is SMM7. As almost all MR credits are based on percentage cost with the cost denominator calculated as per the CSI categories, these credits... Last reply: Eric Johnson, Nov 15, 2011, 7:30 am |
|
we have a training ceterGeneral forumsposted by ola shunnar on Nov 22, 2011, 4:22 am
we have a training ceter building and would like to register it under the CI, and my question is on the MPR, form 2: there is two phrases in the form that make me confused, which are the a)... Last reply: David Posada, Jan 10, 2012, 5:19 pm |
|
Fuel for district energy and electricityNC-2009 MRc2: Construction Waste Managementposted by Tanja Arnesson on Nov 30, 2011, 3:08 amin January- http://www.usgbc.org/DisplayPage.aspx?CMSPageID=2360. LEEDuser will most likely have another Guide and Open Forum as well where you could post your concerns instead for this credit. Susann – Your... Last reply: Keith Robertson, Feb 27, 2012, 11:18 am |
|
ExtensionGeneral forumsposted by Emily Catacchio on Nov 30, 2011, 9:16 am
Jason, Last reply: Susan Walter, Dec 6, 2011, 8:15 am |
|
IE for manual irrigationNC-2009 WEc1: Water Efficient Landscapingposted by Dario Ibarguengoitia on Dec 1, 2011, 6:28 pm
¿what is the IE for manual irrigation? I will use no potable water for this, I will apreciate your response cause asked about this once and did not got an answer, thank you very much Last reply: WAGNER OLIVEIRA SILVA, Dec 8, 2011, 8:55 am |
|
Option 2 Path 4 Heat island Effect nonroofCI-2009 SSc1: Site Selectionposted by Sue Barnett on Jan 30, 2012, 6:38 pm
so my CI LEED project boundary is half of one floor of an 8 story building, it's 14,000 square feet, and does include an exterior courtyard. I interpreted this SS1 credit to mean the conditions... Last reply: Susann Geithner, Feb 16, 2012, 6:36 pm |
|
Using a newer version of 90.1 than what LEED specifiesNC-2009 EAp2: Minimum Energy Performanceposted by Dave H on Feb 1, 2012, 9:53 am
I am working on a project that was registered under LEED NC 2.2. Will the USGBC allow us to apply requirements from 90.1 - 2010 to the project instead of 90.1 - 2004? Specifically what I am... Last reply: Marcus Sheffer, Mar 13, 2014, 9:22 am |
|
Mechanical Ventilation in some areas of buildingNC-2009 EAp2: Minimum Energy Performanceposted by Santiago Rodriguez on Mar 5, 2012, 3:45 pm
Hello, I have the following doubt: Suppose that a building has an HVAC system designed for all office and working areas, but for the restrooms and locker rooms, which are occupied every... Last reply: Marcus Sheffer, Mar 13, 2012, 8:46 am |
|
Particulate Matter RemovalNC-2009 IEQp1: Minimum indoor air quality performanceposted by Paula Hernandez on Mar 20, 2012, 8:52 am