High Voltage Equipment testing scopeCS-v4.1 EAp1: Fundamental commissioning and verificationposted by Daisuke Miura on Jul 11, 2024, 8:30 pm
Hi, I am working on a LEED project as Commissioning Agent. This is a commercial building project that is build from green field in Japan. Sometimes, I am not sure what is the... |
|
Registering for the Pilot CreditPilot-Credits IPpc90: Social equity within the operations and maintenance staffposted by Crissy Haley on Jan 27, 2020, 8:08 pm
Does anyone else have issues with registering IPpc90 - Social equity within the project team pilot credit for a v4 ID+C: Commercial Interiors. It does not appear as an option. I... Last reply: Marelle Davey, Jul 11, 2024, 5:32 pm |
|
Waste handling of process installationNC-v4.1 MRp2: Construction and demolition waste managementposted by Josef Andersen on Jul 11, 2024, 8:15 am
Hi! We are constructing industry buildings for car manufactoring. The project phase are divided between our FM team and the process team. Our FM team are responsoble to desing and... Last reply: Josef Andersen, Jul 11, 2024, 10:25 am |
|
Lighting Boundary Modification- Light Trespass: Option 1. BUG Rating Method Only?NC-v4 SSc6: Light Pollution Reductionposted by Lenka Matějíčková on Aug 30, 2023, 2:30 pm
The LEED manual states that, under certain conditions, the lighting boundary can be modified (e.g.when the property line is adjacent to a public street, alley, or transit corridor, the lighting... Last reply: Afogreen Build, Jul 10, 2024, 9:15 pm |
|
WaterSense Tool available only for US and Canada?CS-v4 WEp1: Outdoor water use reductionposted by Marine Petrosyan on Sep 4, 2023, 6:47 am
The LEED Online forms say, that WaterSense Tool supports only zip codes of US and Canada. Does this mean that the tool is not suitable for projects outside the US and Canada? Thank you.... Last reply: Afogreen Build, Jul 10, 2024, 9:09 pm |
|
lighting zone type for project is located in new development areaCS-v4 SSc6: Light Pollution Reductionposted by Linh Dang on Oct 12, 2023, 5:52 am
Dear all, i am consulting for a project is located in the new development area next to the developed area which has high rise buildings and residential buildings. There are not many... Last reply: Afogreen Build, Jul 10, 2024, 9:06 pm |
|
Irrigation RequirementsNC-v4 WEc1: Outdoor water use reductionposted by Eslam Elshorbagy on Oct 18, 2023, 10:59 am
Hello, We are further developing the details and plant mixes to increase biodiversity for a BD+C new construction. We have an approximately non-irrigated vegetated area of 55,000 sf and a... Last reply: Afogreen Build, Jul 10, 2024, 9:03 pm |
|
"cold in-place recycling" aka "asphalt milling" aka "cold regeneration"NC-v4.1 MRc5: Construction and demolition waste managementposted by Joyce Kelly on Jul 10, 2024, 2:28 pm
This could support this credit and possibly others in the MR and SS categories. Has anyone pursued this within a LEED project? Last reply: Dave Hubka, Jul 10, 2024, 2:52 pm |
|
University/Campus SettingPilot-Credits SSpc129: Comprehensive Compostingposted by Atlas Turner on Mar 30, 2023, 3:38 pm
Hi All, Our project is on a University Campus. The campus has already implemented onsite comprehensive composting and has an active contract with the compost hauler. The campus is not... Last reply: Rebecca Rice, Jul 10, 2024, 2:26 pm |
|
Grey Infrastructure DevicesNC-v4.1 SSc4: Rainwater managementposted by Jason Cocek on Oct 14, 2021, 11:25 am
The LEED v4.1 guidance says that conventional grey infrastructure devices and hard runoff conveyance systems can be used as a component of... Last reply: Dave Hubka, Jul 10, 2024, 2:19 pm |