Water Use Reduction: Base Building with existing fixturesCI-v4 WEp1: Indoor water use reductionposted by Scott Edwards on Jun 13, 2016, 9:04 pm
Hi - We are working on an interior commercial fit out project in a... Last reply: Kate Vawter, Oct 28, 2020, 7:58 pm |
|
Industrial or non-regular process loadNC-v4 EAp2: Minimum Energy Performanceposted by Charalampos Giannikopoulos on Nov 16, 2016, 8:52 am
For a facilities with increased process load (more than 60%), other than data centers, including but not limited to industrial facilities, is there a particular guidance in establishing a... Last reply: Abdullah Tahir, Mar 29, 2024, 1:40 am |
|
The correct/latest 62MZ & LEED min. IAQ spreadsheet?NC-2009 IEQp1: Minimum indoor air quality performanceposted by Aru Sau on Dec 5, 2016, 11:07 am
Is "v2009v4_Minimum... Last reply: Hernando Miranda, Feb 5, 2018, 2:18 pm |
|
Kitchen FaucetsNC-2009 WEp1: Water Use Reductionposted by Angel Vega on Dec 14, 2016, 2:27 pm
The building I am trying to obtain the certification for, is a museum. It has two rooms with faucets for the cleaning staff. Are these faucets into the objetive of reduction? Last reply: Gerren Wagner, Apr 19, 2018, 4:55 pm |
|
Airport base ratio?NC-v4 LTc7: Reduced parking footprintposted by Bouygues Sustainability on Jan 23, 2017, 10:11 am
Hello - how do i calculate the baseline parking capacity of an airport ? - it is not included in the TABLE 1 - Base Ratios for parking spaces, by building type. Last reply: Chris Flint Chatto, May 3, 2022, 4:28 pm |
|
Baseline HVAC System SelectionCS-2009 EAc1: Optimize Energy Performanceposted by Ciaran McCabe on Mar 8, 2017, 11:34 am
I am working on a 9 storey office building (8 levels of office and 1 basement level). The building has a total floor area of 9,400m2. The space heating and cooling will be provided by means of a... Last reply: Marcus Sheffer, Sep 4, 2020, 10:30 am |
|
20% Cut Sheet UploadNC-2009 MRc5: Regional Materialsposted by Denise Domino on Mar 14, 2017, 8:27 amin or register to post comments RETIRED LEEDuser Expert 623 thumbs up March 14, 2017- 11:55 am Check out the January and June 2016 updates on the LEEDuser forum- LEED Online Status Updates-... Last reply: Debra a. Lombard, Mar 29, 2017, 11:22 am |
|
Solid Untreated Wood Window SillsNC-v4 EQc2: Low-emitting materialsposted by Alara Brinton on Jun 26, 2017, 6:01 pm
We have a project installing solid... Last reply: RETIRED, Jan 9, 2018, 7:01 pm |
|
Occupant Comfort SurveyNC-v4 INc1: Innovationposted by Leanne Conrad on Aug 3, 2017, 4:01 pm
Is there a minimum duration after occupancy you must wait to conduct the occupant comfort survey? I want to submit the IN credit with the first construction submittal but don't want to have to... Last reply: Stephanie Graham, Oct 16, 2019, 3:48 pm |
|
metal door in factory-finished metal product exception?NC-v4 EQc2: Low-emitting materialsposted by Charline SEYTIER on Dec 12, 2017, 6:53 am
Hello, We have a question concerning the exception in Wall and ceiling categories on 'factory-finished metal product': Would a metal door completely factory-finished be part of... Last reply: Joanna Switzer, May 23, 2018, 12:23 pm |