Should I consider process water?

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  Nadia Ayala  on 

Hi, My project is a pharmaceutical facility. For their industrial process, they use a fairly large amount of water. I was wondering if process water is considered for this credit.

3
Architect / LEED AP BD+C
KILTIK Consultoría
LEEDuser Basic Member
36 thumbs up
Thu Feb 7, 2013, 10:42 pm
8
LEED AP BD+C, O+M, Green Globes Professional
JLL
LEEDuser Basic Member
112 thumbs up
Thu Feb 7, 2013, 8:31 pm

Include curbs and tops of walls? SRI of granite curb?

NC-2009 SSc7.1:Heat Island Effect—Non-Roof
posted by  Erica Downs  on 

In adding up the "paved" areas, are granite curbs (between the sidewalk and street) typically included?

3
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Feb 7, 2013, 7:05 pm

Thermostat Values

CS-2009 EAp2:Minimum Energy Performance
posted by  Herman C  on 

Hello, How are the Thermostat values (Upper and Lower limit) to be selected for LEED CS please?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Feb 7, 2013, 5:40 pm

Hotel and Convention Center - Registration as One project

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Ahmad Gabir  on 

We have a hotel building (600,000 sf) and a convention center (150,000 sf) which are connected by a 300-400 feet ong corridor.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Feb 7, 2013, 4:34 pm

NC Comercial Building into a LEED ND Neighborhood (Stage 1)

NC-2009 SSc2:Development Density and Community Connectivity
posted by  Gaston Viau  on 

Our project is located into a LEED Neighborhood Development which obtained Stage 1 certification.

3
Thu Feb 7, 2013, 3:52 pm

LEED Canada SS Credit 6.1 - Stormwater - Cistern Sizing

LEED Canada Forum
posted by  Meghan MacSween  on 

Hi, The 2009 version of LEED included an interpretation for the SS6.1 credit stating that controling site discharge using storage such as cisterns could meet the credit requirements even if the en

2
Default Avatar
Mechanical Engineer
Stantec
LEEDuser Premium Member
18 thumbs up
Thu Feb 7, 2013, 1:12 pm

Hazardous Chemical Clarification

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Edward Gulick  on 

The small project I'm working on will have a small janitors closet with a mop basin, as well as a stacked washer/dryer for rags and towels.

2
Default Avatar
Senior Mechanical Designer
LEEDuser Basic Member
0 thumbs up
Wed Feb 6, 2013, 9:49 pm

Differential Pressure Measurement

EBOM-2009 IEQp2:Environmental Tobacco Smoke (ETS) Control
posted by  Oliver Glahn  on 

Hello, has anyone experience in conducting the differential air pressure measurement of a smoking room with respect to each adjacent vertial chase? This requirement seems very difficult to meet.

2
Default Avatar
Project Partner
Drees & Sommer Advanced Building Technologies
LEEDuser Basic Member
2 thumbs up
Wed Feb 6, 2013, 7:03 pm

buidable land

ND-v2009 SLLc6:Steep slope protection
posted by  Noriko Nagazumi  on 

Hi, Is the definition of buildable land under LEED-ND identical to the following statement quoted from http://www.ci.blaine.mn.us/index2col.cfm?id=901246? "The space remaining on a lot after the mi

7
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up