Baseline equal to zero

ND-v2009 GIBp3:Minimum building water efficiency
posted by  Karyn Rodrigues  on 

Hi, I have three buildings within the LEED ND boundary, and one of them is not going to pursue any green building certification.

3
Senior consultant, LEED AP ND & BD+C
Arup
LEEDuser Basic Member
10 thumbs up
Thu Oct 10, 2013, 10:57 pm

ID credit: Aluminum form-work system

NC-2009 IDc1:Innovation in Design
posted by  Eric Carter  on 

Our contractor would like us to consider attempting an Innovation credit for their use of an aluminum form-work system for all of the tilt-up concrete elements built in the project: the intent of t

3
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Oct 10, 2013, 4:55 pm

Exhuast fan and 62.1 compliance

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Jatuwat Varodompun  on 

If we use an exhuast fan for an office and have no clear location of OA intake, can we comply with 62.1?

2
Default Avatar
HVAC consultant
Optimized Systems
LEEDuser Basic Member
19 thumbs up
Thu Oct 10, 2013, 1:06 pm

Tenant design and construction guidelines- CS Sc9

LEED Guidance for Campuses and Multiple Buildings
posted by  Noriko Nagazumi  on 

Hi All, Th Appendix A - AGMBC Applicability for Credits and Prerequisites in LEED 2009 Design & Construction Rating Systems describes a Mater Tenant Design and Construction Guideline for SSc9

2
Technical Customer Service Specialist
GBCI
LEEDuser Premium Member
105 thumbs up
Thu Oct 10, 2013, 11:26 am

Submit a Low Mercury ID Credit

NC-2009 IDc1:Innovation in Design
posted by  Joel Register  on 

I would like to use the EB: MRc4-low mercury bulb credit for an ID credit in a LEED-CI project. What is the process in in submitting this as an ID credit.

8
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Thu Oct 10, 2013, 7:13 am

documentation issue

Pilot-Credits EApc56:Renewable energy - distributed generation
posted by  Noriko Nagazumi  on 

Hi, Our project will lend the rooftop to other company "A" which will install PV panels on the entire roof area and sell generated electricity to utility company. The contract between the project o

4
Director, Sustainability Programs
Digital Realty
LEEDuser Basic Member
3 thumbs up
Thu Oct 10, 2013, 6:45 am

Incomplete Spaces

NC-2009 PIf1:Minimum Program Requirements
posted by  Annalise Reichert  on 

I know that if there are incomplete spaces at the time of certification the owner needs to write a letter of commitment indicating the remaining spaces will satisfy LEED requirements.

2
Thu Oct 10, 2013, 6:21 am

PI form 2 vs Energy Simulation Floor Area

NC-2009 EAp2:Minimum Energy Performance
posted by  Leandro Silva  on 

We have a conflict between the LEED floor area which clearly excludes underground parking (in our case) and the area of the energy simulation.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Oct 9, 2013, 9:59 pm

Separate lighting and plug load sub-metering

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Magnus Stagnäs  on 

Our client’s CS-project has been denied EAc5.2 because we haven’t provided separate sub-metering of tenant lighting and plug loads.

2
Sustainability Manager
YR&G
LEEDuser Basic Member
55 thumbs up
Wed Oct 9, 2013, 9:32 pm

Hotel System 2 Reheat

NC-2009 EAp2:Minimum Energy Performance
posted by  Michael Angell  on 

I am currently modeling a hotel with less than 20,000sqft (specifically 19720) of non-residential space.

6