posted by Lakshmi Suryan on Oct 26, 2014, 6:17 am

If the credit is applied on Metro stations , can i presume that the credit holds good only for office spaces or regularly occupied spaces within the station ? Can I ignore tranisition spaces...

link goes to the main USGBC home page

Pilot-Credits PC14: Walkable Streets
posted by Melissa Merryweather on Oct 28, 2014, 11:00 pm

Hi, I am registered for this Pilot Credit. However, when I went to register my user-name for this credit using your link at the top of this page (step 2) I get a message saying I don't have...

IEQp1 Design Review told me I have multizone not single

CI-2009 IEQp1: Minimum indoor air quality performance
posted by Kasandra Martin on Oct 29, 2014, 9:03 am

I have roof top units. Each serves several rooms. One system serves a single room with single thermostat. However the rest of them serve several rooms and instead of one thermostat to the RTU I...

LEED-H Water Use

Homes-v2008 WEc3: Indoor water use
posted by Robyn Vettraino on Oct 29, 2014, 12:48 pm

Is there a tie-in somewhere that requires individually metered homes/units in LEED for Homes?

Use of greywater

Pilot-Credits WEpc10: Sustainable wastewater management
posted by Noriko Nagazumi on Oct 30, 2014, 9:39 pm

Hi all,

We pursued Pilot Credit WEpc10 through Option 2, and planned to use recycled grey water for flush fixtures.This recycled grey water accounts for 100% reduction in flush water user...

On the other hand...

General forums
posted by Lawrence Lile on Oct 30, 2014, 5:51 pm

I'll certainly not be shedding a tear to be losing the cumbersome LEED V3 LEEDONLINE website, with it's slow-loading, Internet-Explorer-only, buggy SAP interface. That's probably the feature of...

CMU as regional materials

Homes-v2008 MRc2: Environmentally preferable products
posted by Benjie Herrera on Nov 1, 2014, 7:24 pm

Can we achieve .5 pt. of Environmentally preferable product credit if we will be using CMU in the fence/landscaping area/grass area? Is this area considered as exterior wall? Pls. Advise.

showers and lavatories in ammenities area

NC-2009 WEp1: Water Use Reduction
posted by Saju Varghese on Nov 3, 2014, 3:33 pm

Hello,
We currently have a project of an apartment building with 5 FTEs, 8 visitors and 78 residents. It also has an amenities level with shower of 2 gpm and lavatories of 0.5 gpm, that is...

CS appendix 1: default occupancy counts

NC-2009 PIf3: Occupant and Usage Data
posted by Bernadette Stauder-Buschlinger on Nov 5, 2014, 5:17 am

The project is a restaurant within a high rise office building. My question is: What is the correct gross square feet per...

energy-saving target during construction

CS-2009 IDc1: Innovation in Design
posted by Dee Yun on Nov 7, 2014, 1:32 am

Hi, I have a project that has energy-saving target during the construction phase. The intent is to reduce environmental and economic impacts associated with excessive energy use during the...