Topic | Recent |
---|---|
Bio-based products / USDA BioPreferred designationEBOM-v4 MRc4: Solid waste management - ongoingposted by Sarah Martinez on Oct 6, 2014, 1:46 pm
Would a product that is recognized by the... Last reply: Kristen Magnuson, Sep 22, 2017, 8:11 pm |
|
Process loadsNC-v4 EAc2: Optimize Energy Performanceposted by Ake Larsson on Oct 7, 2014, 4:14 am
In our company, we have introduced LEED as mandatory for all new construction projects. but unfortunately LEED is not really made for Factories, where you have quite a high process loads compared... Last reply: Stefanie Young, May 20, 2015, 5:45 pm |
|
Indoor water use Reduction Calculator bugEBOM-v4 WEp1: Indoor water use reductionposted by OSCAR DE LA RED on Oct 7, 2014, 5:04 am
There is a bug in the Indoor water use Reduction Calculator when there is no urinals, the male water closet uses per day are set to 4 instead of 3 uses per day. How can we solve this? Last reply: OSCAR DE LA RED, Oct 7, 2014, 1:19 pm |
|
Exterior lighting powerNC-2009 EAp2: Minimum Energy Performanceposted by VICTOR MORENO on Oct 7, 2014, 11:25 am
Hello. One review comments that i have received about E&Ap2 prerequisite is: 2. No exterior lighting power has been modeled for the Baseline or Proposed Case. Confirm that no... Last reply: Marcus Sheffer, Oct 9, 2014, 7:37 pm |
|
Credits from other Rating SystemsNC-v4 INc1: Innovationposted by Meredith Elbaum on Oct 7, 2014, 4:25 pm
In V3, USGBC had a list of credits from other rating systems that could be innovation credits. For instance... Last reply: Sara Goenner Curlee, Aug 2, 2017, 2:30 pm |
|
Reinforcement Steel in concreteNC-2009 MRc4: Recycled Contentposted by Lise Dannesboe on Oct 8, 2014, 3:26 am
Hi! How is reinforcement steel calculated in an... Last reply: Lise Dannesboe, Oct 9, 2014, 10:36 am |
|
Baseline envelope- Existing Buildings (Retrofit)NC-2009 EAp2: Minimum Energy Performanceposted by João Costa on Oct 9, 2014, 10:11 am
Hello, 1) According to Table 3.1 from Appendix G, thermal loads due... Last reply: Marcus Sheffer, Jul 16, 2019, 4:53 pm |
|
One or two separate buildingsNC-2009 PIf1: Minimum Program Requirementsposted by Felipe Holguin on Oct 9, 2014, 11:56 am
I have a project with two buildings that are attached physically by two underground levels with services as parking spaces, bicycle racks, showers and bathrooms and MEP systems shared for both... Last reply: Brian Salazar, Oct 14, 2014, 9:08 pm |
|
Can you add a new credit while in the Construction Review Phase?LEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Mike Stopka on Oct 10, 2014, 10:22 am
I am working on a project that is currently in the Construction Preliminary Review Phase. We are realizing that Gold Certification is a reality now. Is it possible to add two new credits that... Last reply: Mike Stopka, Oct 10, 2014, 4:36 pm |
|
School with unusually large amount of artificial turfSchools-2009 SSc5.2: Site development - maximize open spaceposted by Helen Kessler on Oct 12, 2014, 9:16 pm
100% of the athletic areas for an urban school are made of artficial turf. It's my understanding that this would be counted as hardscape under SSc5.2. There is a clause in WEc1 that allows a... Last reply: Helen Kessler, Nov 24, 2015, 9:40 pm |