Log in
Forum
Topic

MRpc69- easily achieved, but not always

Pilot-Credits MRpc69: Construction and demolition waste management
posted by Laura Charlier on Jan 9, 2014, 6:05 pm

We registered for this credit for one than one project under the thought that it would be easy to achieve. We were right...for one of the projects. However, because the credit follows the...

Last reply: Joanna Switzer, Apr 9, 2015, 5:57 am

How to calculate effective operable area for top hung window

NC-2009 IEQp1: Minimum indoor air quality performance
posted by SSN Energy Model on Jan 17, 2014, 4:04 am

Hi,
We are in the initial design of an office building. The Project team has planned to provide top hung window & the building will have more naturally ventilated spaces.
How to...

Last reply: Nadia Ayala, Jul 22, 2014, 3:35 pm

LEED-CI renovate 3 floors, entire building has same owner

NC-2009 MPR2: Must be a complete, permanent building or space
posted by Michelle Halle Stern on Jan 17, 2014, 4:44 pm

The commentary above seems contradictory to me. Under CI, complete interior space the MPR stipulates “The LEED project scope must include a complete interior space distinct from other spaces...

Last reply: Michelle Halle Stern, Jan 19, 2014, 1:33 am

Water category questions

General forums
posted by Maria Porter on Jan 23, 2014, 7:47 am

Hi Tristan!
I dug deeper into the water category yesterday and a few questions surfaced:

•Water Metering credit – At least two out of six systems have to be sub metered as applicable...

Last reply: Edward Malesevich, May 22, 2014, 8:51 am

Informal Space in a University Setting

Calculating FTEs
posted by Mike Manzi on Jan 23, 2014, 4:22 pm

Does anyone have any experience with having a large informal waiting space outside of classrooms and determining a transient load. There will be users using waiting in this space before and...

Last reply: Erin Holdenried, Jan 23, 2014, 6:13 pm

Banking facility

NC-2009 SSc2: Development Density and Community Connectivity
posted by Magda Aghababyan on Jan 24, 2014, 11:55 pm

For one of our projects we are thinking of negotiating with a local bank to set up an ATM machine that is open to public. The bank it self is not close by but we can make a deal with them to set...

Last reply: Eric Anderson, Jan 29, 2014, 1:48 pm

Healthcare & Schools- Exterior Requirements

Schools-NC-v4 EQc2: Low emitting materials
posted by Jennifer Gleisberg on Jan 27, 2014, 4:24 pm

What are the exterior paints & coatings requirements for healthcare and school projects with Version 4?

Last reply: Chyanne Husar, Sep 20, 2019, 7:07 pm

Occupant Recycling Program- LEED Interpretation 3920

NC-2009 IDc1: Innovation in Design
posted by Eric Carter on Jan 28, 2014, 1:12 pm

We've attempted to earn an innovation credit by citing the owner's initiative to recycle materials (batteries, motor oil, electronics, cooking oil, and other fluids from industrial equipment)...

Last reply: Tristan Roberts, Feb 20, 2014, 4:18 pm

Regional Priority points in total points attempted

CS-2009 RPc1: Regional Priority
posted by J W on Jan 28, 2014, 1:18 pm

I have completed 4 points that should also be regional priority points, but I don't see anywhere that 4 points have been added. Will they add them after submitted or should they show up in my "...

Last reply: J W, Jan 28, 2014, 3:11 pm

Natural ventilation

NC-2009 EAp2: Minimum Energy Performance
posted by Rosana Correa on Jan 28, 2014, 3:30 pm

We are working on an industrial building which has 3 hangars which are occupied during working hours and its partly open and 24 hours natural ventilated. How should we address this building...

Last reply: Jean Marais, Jan 30, 2014, 3:59 am