ventilation levels

NC-2009 EAp2:Minimum Energy Performance
posted by  Tristan Roberts  on 

I got this question via email and thought I would post it here for your help. Thanks!

4
Default Avatar
Energy Modeler
KJWW Engineering
LEEDuser Basic Member
3 thumbs up
Thu Apr 21, 2016, 7:51 pm

3 LEED projects sitting on a parking & retail layer cake

NC-2009 MRc4:Recycled Content
posted by  Susan Di Giulio  on 

Hi, We have a campus master site occupying a city block. There are 7 podium floors with a hotel, condo towers and retail sprouting from them that are parsed into 3 separate LEED projects.

6
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Thu Apr 21, 2016, 5:50 pm

Bike Racks Calculation for the 1928456ft2 Rapid Train Station

CS-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Rooms
posted by  Orçun Özhelvaci  on 

Dear All, We have confronted with 1 complicated issue regarding Bike Rack numbers. The gross floor area 1.928.456 ft2 Rapid Train Station with its Hotel, Restaurant and Mall.

3
Facilities manager
Prime project International Dubai
LEEDuser Basic Member
0 thumbs up
Thu Apr 21, 2016, 4:16 pm

REVIT 2016 Daylight Analysis Tool not acceptable?

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Deborah Lucking  on 

We submitted for this credit using the results from the REVIT 2016 daylight analysis tool.

2
Default Avatar
LEED AP
ABUD Engineering Ltd.
LEEDuser Basic Member
34 thumbs up
Thu Apr 21, 2016, 12:39 pm

Residential Requirements

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Brightworks Sustainability  on 

Hi all, I am working on a graduate housing project that is all residential, and some apartments have doors directly to the outdoors. What are the walk-off mat alternate requirements in this case?

2
Wed Apr 20, 2016, 3:01 pm

Drop irrigation only when needed

CS-2009 WEc1:Water Efficient Landscaping
posted by  Mathilda Jonsson  on 

I have a similar quesion as Alicja Bieszyńska, had above. Our project will contain offices and a pre-school facility. Two adjacent building contains homes. These buildings will share a large yard.

3
ESG consultant, LEED AP BD+C
Self Employed
LEEDuser Basic Member
36 thumbs up
Wed Apr 20, 2016, 2:07 pm

Multi-Family Buildings with Non-Residential Entrances

ND-v2009 NPDc9:Access to civic and public space
posted by  Sara Zoumbaris  on 

Hi, we have a site with several multi-use buildings which have non-residential entrances and a main entrance which will lead to residential lobby etc.

2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Tue Apr 19, 2016, 8:27 pm

Fire Station FTE

NC-2009 PIf3:Occupant and Usage Data
posted by  Deborah Morgan  on 

I have a fire station that will have 9 fire fighters working 24-hour shifts. 1.

3
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Mon Apr 18, 2016, 8:54 pm

Baseline HVAC for Major Renovation keeping existing chiller

NC-2009 EAp2:Minimum Energy Performance
posted by  Maria Isabel Conde  on 

Hi, we are working on a project for which our client would like to pursue a Major Renovation certification. All air handlers will be replaced.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Apr 18, 2016, 8:34 pm

Alternative Compliance for M&V

NC-2009 EAc5:Measurement and Verification
posted by  Deborah Lucking  on 

All, our project is a large and complex convention center remodel/expansion. We are proposing a metering strategy that is tailored to the way the building will be operated.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Apr 18, 2016, 4:55 pm