OVER HEAD CEILING LIGHTS

EBOM-2009 IEQc2.2: Controllability of systems - lighting
posted by RASHID HAMEEN on Mar 16, 2010, 3:33 am

Our factory is equipped with both task lights at the machinery and with overhead ceiling lights. I want to know whether is it necessary to use control switches both to those or will it be...

Last reply: Tristan Roberts, Mar 17, 2010, 7:11 pm

IDc1 and contractor certification

General forums
posted by Tristan Roberts on Mar 17, 2010, 7:43 pm

I haven't heard of this, but that doesn't mean it doesn't exist. Have you looked for it in the IDc1 catalog that was published by USGBC, showing successful (and unsuccessful) approaches? This is...

IEQ 10 / Natural Ventalation

Schools-2009 IEQc10: Mold Prevention
posted by Thomas Burnham on Mar 11, 2010, 7:07 pm

Is it possible to achieve this credit with a naturally ventilated building located in northern California

Last reply: Tristan Roberts, Mar 18, 2010, 1:32 pm

Commissioning during construction

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Tatjana Ernst on Mar 18, 2010, 12:17 pm

Dear Users,

we have to certify a office bulding - new built - which is already on site.
The structural works ( basement and parts of the first floor) has started
already. Our...

Last reply: Jean Marais, Mar 19, 2010, 3:25 am

Efficiency calculation

EBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiency
posted by RASHID HAMEEN on Mar 16, 2010, 7:47 am

We are planing on pursuing LEEDS for one of our Garment manufacturing facilities. At the moment we are trying to see the status of our water usage compared to the baseline.

We bought the...

Last reply: Jason Franken, Mar 19, 2010, 12:08 pm

Sub metering clarification

EBOM-2009 WEc1: Water Performance Measurement
posted by RASHID HAMEEN on Mar 17, 2010, 3:18 am

Ours is a production facility which we are intending to achieve LEED. We have the main production building and other supportive building spaces (Canteen, hostels and toilets which are separate...

Last reply: Jason Franken, Mar 19, 2010, 12:30 pm

Is this Decision Final?

Air Sealing Guidance for LEED BD&C IEQp2
posted by April Ambrose on Mar 17, 2010, 12:55 pm

Based on these comments it seems to me that you are saying blower door tests are required for any residential projects, whether smoking is allowed within the building or not. Does this answer my...

Last reply: Tristan Roberts, Mar 19, 2010, 12:38 pm

Recertification question

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by Matthew Macko on Mar 18, 2010, 7:47 pm

In five years’ time (or less), when an owner goes to get the building recertified under...

Last reply: Jason Franken, Mar 19, 2010, 12:42 pm

EQ c7.1, 2.2 for naturally ventilated buildings in mild climate

NC-2009 IEQc7.1: Thermal comfort - design
posted by Mara Baum on Mar 17, 2010, 9:52 pm

I am working on a pair of naturally ventilated dormitories in a relatively cool/mild climate -- the highest mean monthly temperature is 76 degrees F and the RH is between 60-70%, with some...

Last reply: Gunnar Hubbard, Mar 19, 2010, 2:43 pm

refrigerant quantities as a % of the overall project equip.????

CI-2009 EAp3: Fundamental Refrigerant Management
posted by sara frye on Mar 11, 2010, 12:15 pm

We have just received our review acknowledging our phase out plan for CFC based equipment. The next line reads "However the refrigerant quantities as a percentage of the overall equipment has...

Last reply: Dan LeBlanc, Mar 19, 2010, 5:42 pm