Inconsistency between BD+C and O+M
CS-v4 EQc1:Enhanced indoor air quality strategiesposted by Adam Stoker on
Despite efforts to better align the rating systems in LEED v4, there are some inconsistencies between the Enhanced Indoor Air Quality Strategies credits in BD+C and O+M.
Duct Insulation to meet ASHRAE 90.1
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Ralph Bicknese on
We have a condition at where the contractor has asked to use blue duct for underground locations in lieu of Armaflex insulation and concrete encasement.
µg not µm?
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Takayuki Hirota on
Reference guide Addenda allows to use filtration media with a minimum dust spot efficiency of 30% or higher and greater than 90% arrestance on a particle size of 3–10 "µg". I suppose it is "µm" no
Modeling semi heated space with mechanical ventilation
NC-2009 EAp2:Minimum Energy Performanceposted by Ashwin Kumar on
We are working on the energy modeling for Industrial Manufacturing facility in which some places can be classified as “Semi heated spaces” as per ASHRAE 90.1 2007 definition.
Very high density in a rapidly developing area
NC-2009 SSc2:Development Density and Community Connectivityposted by Susan Di Giulio on
Hi, Our project is a campus filling a city block across the street from the premier sports stadium, a huge entertainment complex and a convention center in major US city.
Extending the project boundary after Preliminary review
EBOM-2009 PIf4:Schedule and Overview Documentsposted by Szymon Zwoniarkiewicz on
We are in the process of pursuing LEED EBOM certification, for a project located in Europe. We have submitted the documentation for preliminary review.
Change energy consumption data after Preliminary review
EBOM-2009 EAp1:Energy Efficiency Best Management Practicesposted by Szymon Zwoniarkiewicz on
We are in the process of pursuing LEED EBOM certification, for a project located in Europe. We have submitted the documentation for preliminary review.
revolving doors
NC-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Anastasia Makarenko on
Dear all, could you please help me with the following question - on our project we have revolving doors with entryway systems installed, its diameter is 2,8 m.
Group Project - WEp1 & WEc3
Healthcare-v2009 WEp1:Water use reductionposted by Emily Hope on
In group projects, the WEp1 form requires data to be submitted separately for each project building.
Miles per gallon
EBOM-2009 SSc4:Alternative Commuting Transportationposted by Jennifer Webb on
Hello, We are conducting a survey with government employees and are trying to reduce the survey length as much as possible. Do miles per gallon (mpg) need to be included in the survey or would ma