LEED for Multi-Family Homes Bicycle Security
Pilot-Credits PC13:Bicycle Network, Storage, and Changing Roomsposted by Nicole Koedyker on
For the bike storage at this location, our intent is to create closets similar that can be locked, which would certainly meet this requirement.
Full list of
posted by Michael E. Edmonds-Bauer on
I was checkin the USGBC website looking for more LEED interpretations that could give us a hand in documenting SSc4.3.
Hi all, (I posted this
posted by Diaa Madkour on
Hi all, (I posted this comment under MPR section but thought it may apply here too) My company received a request for proposal to work as LEED assessor for three office buildings under core and she
Building Reuse
NC-2009 MRc1.1:Building Reuse—Maintain Existing Walls, Floors and Roofposted by Tristan Hughes on
Hi All I am new to LEED so please excuse me if this question is a little simple. We are building a new office building on the side of an existing office, and the new office is more then 2 times the
Cost of a whole building LCA and providers?
Pilot-Credits PC1: Life-Cycle Assessment (LCA) of Building Assemblies and Materialsposted by rw speer on
Is there a list somewhere of service providers that will do an LCA on your building? What do they charge?
Changing rooms
CI-2009 SSc3.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by MARIA GARCIA on
Hi all, We have the showers of the project inside the ADA bathroom due to lack of space in the project.
Gross Area=Regularly occuppied + Unconditioned
NC-2009 PIf3:Occupant and Usage Dataposted by Alicia Villanueva on
We've been requested be the reviewer that the sum of regularly occuppied areas plus the unconditioned spaces mus be equal to the total gross area. We have not been requested this issue in previous
Mixed bathroom
NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Alicia Villanueva on
Do mixed bathrooms count towards this credit? We have showers in the building but we don't have them separated for both female and male.
Translation to american english
NC-2009 PIf4:Schedule and Overview Documentsposted by Alicia Villanueva on
Is it mandatory to translate the mechanical drawings to american english. The project is originally designed in spanish. GH
Baseline Fan power
NC-2009 EAc1:Optimize Energy Performanceposted by S Gopikumar on
I’m modeling a typical office building which operates 5 days/40 hours per week. In order to comply with G.3.1.2.4, I broken out the fan power from system EER.