Shower calculation

Pilot-Credits PC13:Bicycle Network, Storage, and Changing Rooms
posted by  Michael Smithing  on 

We have 330 FTE and 2 showers. The credit requirement is 1 shower for the first 100 FTE and 1 for each subsequent 200 FTE.

1
Tue Mar 27, 2012, 1:55 pm

Slow Data Entry

Living with LEED Online - quirks, bugs and hiccups
posted by  Brian Baril  on 

I am using IE to upload data into the materials credits, and the process is just mind-boggingly slow. To tab between cells on the online form takes a minimum of 10 seconds.

1
Mon Apr 23, 2012, 2:22 pm

Baseline PTAC sizing

NC-2009 EAp2:Minimum Energy Performance
posted by  April Ambrose  on 

I have a residential facility seeking LEED v2009 certification with small room loads (approx 2,000 BTU/hr).

1
Tue Mar 27, 2012, 5:11 pm

Existing Parking Lot

NC-2009 SSc4.4:Alternative Transportation—Parking Capacity
posted by  Dan Forino  on 

For a NC 2009 project we are building an addition to a building on an which will replace part of an existing campus parking lot.

1
Fri Apr 6, 2012, 2:41 pm

v2009 NC Split Review

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Francisco Villela  on 

I have just submitted Design Preliminary Review for my project.

1
Wed Mar 28, 2012, 12:16 pm

Confidential Materials Cost Budget

CI-2009 MRc4:Recycled Content
posted by  samala hartley  on 

This LEED CI project would like to maintain privacy in regards to their materials budget.

1
Tue Apr 10, 2012, 10:34 pm

7 Year Lease and 5 Year Option to Renew

CI-2009 MRc1.1:Tenant Space—Long-Term Commitment
posted by  Crissy Tsai  on 

The tenant has a 7 year lease currently with an option to renew for 5 years. Would this comply with the 10 year lease option. Crissy

1
Wed Mar 28, 2012, 5:47 pm

4" Slab on Grade STC rating

Schools-2009 IEQc9:Enhanced Acoustical Performance
posted by  renee jimenez  on 

The first floor of my classrooms are slab on grade which per the LEED template should have an STC of 50 because its ajacent to the outdoors (grade being the outdoors).

1
Wed Mar 28, 2012, 1:11 pm

Should we consider Hotel Room Showers?

NC-2009 WEp1:Water Use Reduction—20% Reduction
posted by  Francisco Sanchez Arroyo  on 

Should we have to consider the shower heads of the guest rooms?

1
Wed Mar 28, 2012, 10:04 am

Smoking During Construction

Schools-2009 IEQc3.1:Construction IAQ Management Plan—During Construction
posted by  Jessica Diaz  on 

Our project is a school located in Puerto Rico, where the tropical climate allows for natural ventilation and where we don't use the HVAC system during construction.