Forum quick links
City Street Parking Around Site
NC-2009 SSc4.4:Alternative Transportation—Parking Capacityposted by Sara Zoumbaris on
We are working on a major renovation of 3, connected parcels in a major metropolitan area. Our project itself is including no new parking.
Reduced Mercury Content
CI-2009 IDc1:Innovation in Designposted by Lou Niles II on
Hello, We have multiple projects in LEED v2009 for which we could earn this ID Credit and point for but the process of documentation seems quite ridiculous using the EBOM method of "required" or no
Responses to preliminary review comments
NC-2009 EAp2:Minimum Energy Performanceposted by David Browne on
My engineers' submittal for this prerequisite resulted in a lengthy list of comments, with a requirement that a narrative response to each comment be provided.
LEED Project Boundary, Concerned about Future Buildings...
NC-2009 PIf2:Project Summary Detailsposted by Rachel Manoguerra on
I registered a utility training center as an individual project on LEED Online, because at the time that was our understanding.
Two Commissioning Agency
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Steve Valev on
We are documenting a project where a roof-mounted PV system was installed after the building was occupied and the original commissioning process was complete.
minimum drawdown rate
EBOM-2009 SSc6:Stormwater Quantity Controlposted by ethan adams on
OK it seems like, from reading the questions and responses here, that there is absolutely no clear guidance on how to come up with the "rainfall interval event" in order to perform the drawdown cal
Items that are used for either MRc4 or MRc3
NC-2009 MRc4:Recycled Contentposted by Erika Duran on
Dear All, I am unclear about something. If I have items that would qualify for MRc3 but we are not pursuing that credit, is it acceptable to count them towards MRc4?
Re-commisioning
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by John Wood on
I am a PE who has been approached by a building owner with a request to have the building "re-commissioned." I have designed LEED projects before, and participated in the original commissioning, b
NC-v4 LTc2: Sensitive land protection/Wetland Protection
NC-v4 LTc2:Sensitive land protectionposted by Robyn Dowsey on
Is there a precedent anywhere for getting this credit with wetland mitigation plan where small inactive wetlands were included in the project footprint but an equal or greater wetland area was purc
Option 2
NC-v4 SSc4:Rainwater managementposted by henry nguyen on
Hello, I wonder how should I understand Opt.2 BD+C Rain water Mgmt credit. "Manage on site the annual increase in runoff volume from the natural land cover condition to the post-developed conditio