Forum quick links
Solar Reflectance of Porous Playground Paving Materials
NC-v4 SSc5:Heat island reductionposted by Steven Burke on
The reference guide does specifically mention that playgrounds are one of the non-roof areas that should receive shading, though after the one line where playgrounds are mentioned in parentheses, t
Additions While Project is in Certification Review Process
Schools-2009 PIf2:Project Summary Detailsposted by Robert Fiala on
We have a large school project (340,000 sf) that has been submitted for the design phase review and all design phase points are reviewed and marked as anticipated.
Site Boundary Including Other Structures
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Vicki Rybl on
We are certifying a ~30K sf building that shares its site (legal parcel) with a large 8 story garage.
DES Option 1 - Baseline System Heating Type Modeling Guidance
Healthcare-v2009 EAc1:Optimize energy performanceposted by Mike Ramos on
Hi all, I'm hoping someone can clarify how to model the ASHRAE Baseline systems in compliance with the "Treatment of District or Campus Thermal Energy in LEED v2 and LEED 2009 - Design and Constru
Zero lot line
EBOM-v4 SSc5:Site managementposted by Lawrence Lile on
Can a zero lot line building achieve this credit?
LEED Selection - High Rise Residential
posted by Curt Pascoe on
I am working on a unique project. 30 story existing historic building, office.
Natural Ventilation
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Benjamin Cullum on
Under option 2 How do you determine how many sampling stations are needed in a building that is uses Natural ventilation?
Combined Purchasing
EBOM-v4 MRp1:Ongoing purchasing and waste policyposted by Ryan Hoffman on
The project in question is the north building of a 2-building, 1 million sf facility.
ENERGY STAR web services through utilities
EBOM-2009 EAp2:Minimum Energy Efficiency Performanceposted by Kimberly Hosken on
We have the opportunity to push our utility data to ENERGY STAR from our utility company. There are now about a dozen utilities doing this in the USA.
Tri-gen
NC-v4 EAp2:Minimum energy performanceposted by Victoria Watson on
Hi, I am QA'ing a model for a building that will be fed via a cogeneration plant (with absorption chillers) and therefore is a little complicated.