Exhaust fan for chemical storage

CI-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Yaser Al Sharif  on 

If We have chemical storage room with 69.4 ft square in Area in our building , i want to install one exhaust fan for this room to acheive credit requirements , how can i calculate minimum pressure

1
Mon Apr 13, 2015, 2:58 pm

Proposed case outside airflow rates

NC-2009 EAp2:Minimum Energy Performance
posted by  Cagril Comert  on 

Hi, Our office building is ventilated with a constant volume AHU and conditioned by VRF system. AHU supplies 100% fresh air to the spaces, while VRF system provides heating and cooling.

1
Tue Jul 11, 2017, 3:54 pm

Temporary Materials - Formwork

NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials
posted by  Christopher Drew  on 

The materials credits apply to components that are permanently installed in the building.

1
Wed Aug 19, 2015, 12:18 pm

Building footprint

NC-2009 SSc5.2:Site Development—Maximize Open Space
posted by  Febin Mohamed  on 

We are doing a campus approach for our project.

1
Tue Jan 17, 2017, 10:46 pm

water cooled chilller

NC-2009 EAp2:Minimum Energy Performance
posted by  sherif el adly  on 

Hi Marcus The building size is mandating to model the baseline with a water cooled chiller and I will compare the baseline with the design which is using HVAC that is (air cooled chiller + ice sto

1
Thu Dec 1, 2016, 5:40 pm

LEED EBOM

LEED Rating System Selection
posted by  Srimannarayana NCVK  on 

Hi, We are working on a project in Dubai. The building is 55% office and 45% hotel.

1
Sun Dec 7, 2014, 10:37 pm

LEED boundary for a railway station

NC-2009 PIf1:Minimum Program Requirements
posted by  Juan Sergio Simborio  on 

LEED NC 2009 Our project is a major railway station in Qatar.

1
Thu Dec 19, 2024, 4:28 am
1
Tue Jun 6, 2017, 3:58 pm

refrigerant reccovery

NC-2009 EAp3:Fundamental Refrigerant Management
posted by   Faisal   on 

in EAp3 it says that there should be an EPA approved refrigerant recovery technician, is this requirement also for temporary units(like site offices site warehouse etc) or it is only for permanentl

1
Mon Aug 28, 2017, 9:44 pm

Regularly Occupied Space Area Calculation

NC-2009 PIf3:Occupant and Usage Data
posted by  ESRA OZKONUKSEVER  on 

Dear All, While calculating the squarefootage of the regularly occupied spaces in a project building, do we use the gross or the net area of the spaces? Thank you!

1
Fri Nov 27, 2015, 7:14 pm