RECs for project supplied by campus central utility plant?
NC-v4 EAc7:Green power and carbon offsetsposted by Erin Holdenried on
Can RECs be used for project located on a campus with a central plant that generates its own electricity for the campus? It is a cogen plant that also supplies steam and chilled water.
Low Emitting Materials Calculator and Precast Wall Panels
NC-v4 EQc2:Low emitting materialsposted by Teaaron Frye on
In regards to the low emitting materials calculator (v4.1) what is the proper way to document insulated and non-insulated precast concrete wall panels.
Definition of "one building"
CS-v4 MPR2:Must use reasonable LEED boundariesposted by James Jin on
Hi all,
ASHRAE 90.1 all electric baseline?
NC-v4 EAp2:Minimum energy performanceposted by Kevin Gilleran on
Hi all,
Situation:
Central shower amenities, but outside LEED boundary
NC-v4 LTc6:Bicycle facilitiesposted by emily reese moody on
Has anyone had any luck documenting showers available outside of their boundary, like in a campus environment? Our project is an academic classroom building in the middle of a university campus.
Perimeter light levels affected by surrounding sites.
EBOM-v4.1 SSc3:Light Pollution Reductionposted by Rick Walls on
The perimeter light levels are driven by the surrounding light sources such as street lights and adjoining building lights. Do I need to make note of these factors in the credit form?
Recommended Specs for Commercial Washing Machines?
NC-v4 WEp2:Indoor water use reductionposted by Annalise Dum on
Hello! We are having a FIELD DAY trying to find a compliant commercial washing machine for our hotel project.
Pilot -All-Gender Restrooms
CI-v4 INc1:Innovationposted by Laurie Johnson on
I am pursuing the ALL-Gender Restrooms Innovation. Under Requirments for ID+C it reads Restrooms must be included within the project scope of work in order to pursue this pilot credit.